6
Preparing Installation
Tools and Evironment Requirements
To ensure the outdoor AP set is in good condition for a long
time, the system shall work under the specified operating
environment. Avoid strong vibrations or noises and keep
away from step-down transformer substations and traction
substations as far as possible when installing and debugging
the outdoor AP equipment.
Please prepare the tools and
instruments at all installation stages in advance to avoid
work delay on site.
Item
Requirement
Environment
Operating temperature: -30
℃
~65
℃
Relative humidity: 0%~95% noncondensing
Ingress protection: IP68
Wind speed:
<
250 km/h
Site selection
Away from evironments that are high
humidity, the gas harmful, inflammable,
explosive, vulnerable to electromagnetic
interference (such as large radar station,
fire station and transformer substation) and
voltage unstable:
• It is not recommended to be installed
close to the sea. 500m away from seaside
is suggested
• Avoid ponding places. It is recommended
to be installed on a cement terrace or
where the terrain is high
Grounding
connection
Grounding cord: ≤30m
Type
Tool
General
Adjustable wrench, plier, phillips screwdriver,
sleeve, steel tape, marker pen and percussion
drill
Specialized
Wire stripping plier, wire clamp, waterproof
mortar, waterproof tape and electrical tape
Auxiliary
Ladder
Note: the installation tools are not provided with the
equipment. Please prepare installation tools according to the
real evironment.