22
L531
2,
1
675D
.0/
10.
10
Installation and initial start-up
Fig. 5-2 TFG installed in horizontal position
You can find the nominal values in appendix (section
, page 33) and pin
assignment for DIN 8 plug (see
).
1a
Only for TFG 1..: Connect a suitable control unit (see
, page 16), using
the DIN 8 plug.
1b
Only for TFG 5.., TFG 9..: Open the control unit housing with a suitable tool.
2
Connect the mains cable.
2.1a
Only for TFG 5.., TFG 9..: Connect the mains cable to the mains cable ter-
minal blocks (see positions
and
2.1b
Only with mains cable feed through option (see
the mains cable to the mains cable terminal block (see positions
)
or,
on the final plate, at the terminals for the
mains feed through (
).
Important: The mains supply must only be provided from one side. The mains cable
conductor wires must be stripped from the insulation for a length of 5-6 mm to
ensure a reliable connection. Note the correct configuration of the stranded con-
ductor for the mains cable, in particular, the differences between the mains cable
terminal blocks in the control unit housing and the ones on the final plate.
3*
Only for TFG 5.., TFG 9..: Attach the mains cable, using the strain relief (
4a
TFG 1..: Check if a suitable operating element (see
, page 16) has been
connected to the control unit.
4b
TFG 5.., TFG 9..: Connect the corresponding operating element to the operation
element connection (position
and/or, if the relevant option has been selected, position
in
on the final plate).
5
Check that all interfaces and connections have been mounted and/or connected
correctly.