Commissioning
5 Commissioning
5.1 M-SHEV-10-AP
Place the pair of batteries on the bottom plate of the
housing.
Connect the battery from the black “–” and red “+” battery
connection cables and the attachment cable.
Connect the PE cable to the PE connection on the lid.
Fit the lid and fasten it at the side using the two screws.
The lid has symmetrical fastening features, i.e. it can be
used on the “right” or “left”. The lid can alternatively be
equipped with a lock.
5.2 M-SHEV
Place the pair of batteries on the bottom plate of the
housing.
Connect the battery using the black “–” and red “+” bat-
tery connection cables and the attachment cable.
Figure 25: Battery connection
Ensure that the PE connection is attached to the lid.
Figure 26: PE connection
ATTENTION
The battery may only be connected once
permanent on-site power supply or mains
supply is ensured.
If the mains supply is not permanently en-
sured during commissioning, there is a risk
of total discharge. This causes damage to
the battery.