START-UP
START-UP CYCLE
1.Open the water tap/valve and switch ON the
power on the electrical supply line.
2.The models SVD 152-222-
203-303 enter in the Start Up
cycle with the PC Board
energized, and SVD 503 enter
in 90 minutes delay time
controlled by PC Board, The
LED of ICE MAKING blinking
slow.
In Start Up cycle the LED of
ICE MAKING and BIN FULL
are energized, blinking slow3
minutes for water system
clean, then ICE MAKING
blinking fast 40 second for
pressure balance.
3. During the start up cycle the components in
operation are:
• Hot Gas valve
• Water Drain Valve
• Water Inlet Valve
• Water Pump
FREEZING CYCLE
1. After the start up cycle the machine enters
directly into the freezing cycle with the following
components energized:
• Water Inlet valve
• Compressor
• Fan motor.
2. The LED energized are:
• Machine under power (steady)
• Machine in ICE MAKING (steady)
3. Water is coming into the water through the
Water Inlet Solenoid Valve till the water
reservoir if filled up to the maximum level
controlled by a Water Level Sensor.
4. 40 seconds later, the Water Pump starts up.
5. After few minutes (3-5) from the start up of
the freezing cycle, the Water Inlet Solenoid
Valve is activated again for few seconds to refill
the water reservoir up to the maximum level so
to reduce any possibility of slush ice formation.
6.In the meantime the condenser sensor starts
to transmit the current to the PC Board keeping
in operation the Fan Motor in ON-OFF mode or
continuously according to the condenser
temperature.
7. The machine remains in the freezing cycle
with the ice that become thicker till the two
metal plates of the Ice Thickness Sensor are
covered by the water cascading through the
front surface of the ice plate.
8. When the Power is transmitted back to the
PC Board continuously through the metal
plates of the Ice Thickness Sensor for more
than 6", the machine enters in the Pre-Harvest
or directly into the Harvest Cycle mode
according to:
• FAN MOTOR IN ON-OFF MODE DURING
Rise up the cutting temperature of the
condenser sensor to38
℃
(fan motor off) and
extend the length of freezing cycle by 30" more
the going to harvest cycle.
• FAN MOTOR ALWAYS IN OPERATION
Go straight to the harvest cycle.
9. First freezing time will range between 15 and
NOTE:
Model SVD503 has a crankcase heater in
the compressor. When the main power to the
machine is switched ON, there is a time
delay of 90 minutes during which only the
compressor heater is energized with Green
ICE Making LED Blinking slowly.
However, if the ambient temperature is
higher than 25*C (77*F), PC Board will
automatically bypass this delay.
This time delay can also be bypass by
pressing the bypass switch located at the
back of the machine.
NOTE:
Do not remove the evaporator
deflector cover as it will cause the switching
off of the machine at "STORAGE BIN FULL".
Содержание SVD 152
Страница 4: ...3 SPECIFICATIONS MODULAR CUBER SVD 152 222 Ice Making Capacity...
Страница 6: ...5 SPECIFICATIONS MODULAR CUBER SVD 152 222...
Страница 8: ...7 SPECIFICATIONS MODULAR CUBER SVD 203...
Страница 10: ...9 SPECIFICATIONS MODULAR CUBER SVD303...
Страница 12: ...11 SPECIFICATIONS MODULAR CUBER SVD503...