Commissioning
8.8 Drive optimization
SINAMICS DCM DC Converter
Operating Instructions, 12/2018, A5E34763375A
337
Procedure
●
Start the quick commissioning with p0010 = 1 (= factory setting)
●
Set all of the important parameters (see e.g. commissioning steps in Chapter
"Commissioning using the BOP20" operator panel)
●
Complete the quick commissioning with p3900 = 3 (calculations are performed, p0010
and p3900 are reset to 0)
Commissioning using the BOP20 operator panel:
This procedure is explicitly explained for the commissioning steps in Chapter
"Commissioning using the BOP20 operator panel (Page 273)".
Commissioning using the AOP30 operator panel:
Quick commissioning is completed (p3900 = 3) as part of the final confirmation. (See
Chapter "Full drive commissioning (Page 283)").
Commissioning using the STARTER commissioning tool:
The completion of quick commissioning (p3900 = 3) is selected as part of "Complete" of the
Wizard "Configuring the drive unit". (See Chapter "Configuring a drive unit (Page 298)").
After successfully "Loading the project into the target system" (see Chapter "Starting the
drive project (Page 317)"), quick commissioning is completed in the SINAMICS DCM.
Optimization runs
WARNING
Unexpected motor movement during optimization runs
Optimization runs cause movement of the drive which can result in death, severe injury or
material damage.
•
Observe the general safety instructions.
•
Ensure that the EMERGENCY STOP functions are fully functional when commissioning
the drive.