7.3
Measuring the insulation resistance before commissioning
Measuring the insulation resistance and polarization index (PI) provides information on the
condition of the machine. It is therefore important to check the insulation resistance and the
polarization index at the following times:
● Before starting up a machine for the first time
● After an extended period in storage or downtime
● Within the scope of maintenance work
The following information is provided regarding the state of the winding insulation:
● Is the winding head insulation conductively contaminated?
● Has the winding insulation absorbed moisture?
As such, you can determine whether the machine needs commissioning or any necessary
measures such as cleaning and/or drying the winding:
● Can the machine be put into operation?
● Must the windings be cleaned or dried?
Detailed information on testing and the limit values can be found here:
"Testing the insulation resistance and polarization index" (Page 47)
7.4
Greasing the roller bearings prior to commissioning
The following information assumes that the specified storage conditions have been complied
with.
General specifications
● Pay attention to the instructions on the lubricant plate.
● Regrease in portions. The shaft must rotate so that the new grease can be distributed in
the bearings.
Regreasing the roller bearings prior to commissioning
● If the period between delivery and commissioning is more than a year and less than four
years:
– Re-grease the roller bearings with twice the amount of grease specified on the lubricant
plate.
– Check the bearing temperature, as far as possible.
Regreasing roller bearings before commissioning
You must regrease the roller bearings under the following conditions:
● If the machine has been in storage for more than four years.
● If the machine has not been stored in accordance with the specifications in the "Storage"
section.
Start-up
7.3 Measuring the insulation resistance before commissioning
SIMOTICS TN Series N-compact 1LL8
84
Operating Instructions 11/2018
Содержание SIMOTICS TN 1LL8
Страница 2: ...15 11 2018 10 24 V17 00 ...
Страница 12: ...Table of contents SIMOTICS TN Series N compact 1LL8 12 Operating Instructions 11 2018 ...
Страница 26: ...Description SIMOTICS TN Series N compact 1LL8 26 Operating Instructions 11 2018 ...
Страница 62: ...Assembly 5 3 Installing the machine SIMOTICS TN Series N compact 1LL8 62 Operating Instructions 11 2018 ...
Страница 98: ...Operation 8 9 faults SIMOTICS TN Series N compact 1LL8 98 Operating Instructions 11 2018 ...
Страница 132: ...Spare parts 10 14 Terminal box 1XB9600 SIMOTICS TN Series N compact 1LL8 132 Operating Instructions 11 2018 ...
Страница 136: ...Disposal 11 5 Disposal of components SIMOTICS TN Series N compact 1LL8 136 Operating Instructions 11 2018 ...
Страница 138: ...Service and Support SIMOTICS TN Series N compact 1LL8 138 Operating Instructions 11 2018 ...
Страница 142: ...Quality documents SIMOTICS TN Series N compact 1LL8 142 Operating Instructions 11 2018 ...
Страница 147: ......