PAC 4DI/2DO expansion module
Manual, 11/2018, L1V30545465B-01
17
5
Commissioning
5
5.1
Overview
Requirements
1. The expansion module has already been installed.
2. The expansion module and the PAC device have been connected up correctly.
Note
Check the connections
Failure to connect up the device correctly can result in malfunctions and failure of the device.
Before you start commissioning the device, check that all connections are correct.
Note
When performing an insulation test of the entire installation with AC or DC, disconnect the
device before starting the test.
5.2
Setting expansion module parameters
The parameters for the expansion module can be set either directly on the PAC display or
via the communication interface of the PAC device using the SENTRON "powerconfig"
configuring software.
The SENTRON powerconfig configuration software can be downloaded from the Industry
Online Support Website (
https://support.industry.siemens.com/cs/ww/en/view/63452759
).
Setting parameters on the PAC device
When the SENTRON PAC 4DI/2DO expansion module is mounted on the SENTRON PAC
Power Monitoring Device, you can make the configuration settings for the external digital
inputs and digital outputs.
Select the menu item "SETTINGS" in the SENTRON PAC device menu.
In the menu item "EXPANSION MODULES" select the "4DI/2DO MODULE" that you want to
configure.
For unambiguous module identification, the expansion module slot "MOD 1" or "MOD 2" that
is used is specified in addition to the module designation.
Содержание SENTRON 7KM PAC 4DI/2DO
Страница 1: ......
Страница 2: ......
Страница 6: ...Table of contents PAC 4DI 2DO expansion module 4 Manual 11 2018 L1V30545465B 01 ...
Страница 28: ...Commissioning 5 3 Access via MODBUS PAC 4DI 2DO expansion module 26 Manual 11 2018 L1V30545465B 01 ...
Страница 36: ......