Installing HiPath 3000
Installing HiPath 3800
4.2.11
Performing a Visual Inspection
Introduction
Before starting up the system, you must perform a visual inspection of the hardware, cables,
and the power supply. The procedure is shown in Table 4-9. The visual inspection must be per-
formed while the system is disconnected from the power supply.
Visual Inspection Procedure
7
Caution
Before beginning work, make sure that the system is grounded and disconnected
from the power supply.
Observe the measures for protecting electrostatically sensitive devices (see Page 1-
9).
Table 4-9
Visual Inspection Procedure
Step
Activity
Resources/
Remarks
Action
1.
Compare the slots of the
available boards with the
component mounting dia-
gram.
Board assign-
ment map
If necessary, correct the board config-
uration and notify the sales depart-
ment.
2.
Check that all boards are
secure.
See Page 4-34 If necessary, plug the boards in again.
3.
Check that a shielding cover
has been attached for all
boards with no connection
options in the front cover.
If necessary, replace missing shield-
ing covers (refer to Page 4-35).
4.
Check whether the slots for
LUNA2 and for REALS (ba-
sic cabinet only) are cov-
ered by an outer panel.
If necessary, attach the outer panel
(see Page 4-36).
5.
Check whether all system
cabinets have been sealed
at the rear with the connec-
tion and filler panels provid-
ed.
Get additional connection and filler
panels where required.
Содержание HiPath 3000 V3.0 or later Gigaset M1 Professional
Страница 1: ...HiPath 3000 V6 0 HiPath 5000 V6 0 Provisional Service Manual ESHB 60 004 05 09 22 09 05 ...
Страница 1168: ...Figures P31003 H3560 S403 54 7620 09 05 W 12 HiPath 3000 V6 0 HiPath 5000 V6 0 Provisional Service Manual hp3hp5shLOF fm ...
Страница 1178: ...Tables P31003 H3560 S403 54 7620 09 05 X 10 HiPath 3000 V6 0 HiPath 5000 V6 0 Provisional Service Manual hp3hp5shLOT fm ...
Страница 1201: ......