Alarm verification concept (AVC)
Open service menu / Select menu item
7
29 | 40
Building Technologies
009310_l_en_--
Fire Safety
2018-08-29
7 Alarm verification concept (AVC)
The 'Alarm Verification Concept' serves the purpose of delayed alarm transmission
and takes into account the interaction of the operating personnel in the alarming
sequence.
Operating personnel are able to examine the indicated fire location in the event of
a fire alarm. In the event of a ↑ false alarm or ↑ minor incident, the intervention of
the fire brigade can be avoided.
Information flow of 'ALARM' and 'Pre-ALARM'
D
↑ 'Detection tree'
AL ↑ 'Pre-ALARM' / 'ALARM'
AVC Alarm verification concept
GS ↑ Danger levels
1
↑ 'Area'
The 'Area' receives 'Pre-ALARMS' or 'ALARMS' from 'Zones'. Alarm verification
takes place at 'Area' level.
Configuration for 'Pre-ALARMS' and 'ALARMS' is not related within 'AVC'. The type
of verification and alarming can be separately configured for the 'Manned
operation' and 'Unmanned operation' operation modes.
'ALARMS' of 'Manual zones' and 'Automatic zones' 'Zones' as well as 'Degraded
FIRE ALARM' can be configured differently.
A maximum of one 'AVC' is possible per 'Area'.