English 04/00 BT 200
(S)J31069-D0075-U001-A2-6318
Page 4
2 Commissioning
Before initial commissioning, check your deli-
very, and charge the battery.
Scope of delivery
The delivery includes:
-
1 BT 200
-
1 battery
-
1 test plug connector (wiring test)
-
1 test cable, length: 2 m (station test)
-
1 user’s guide
Charging the battery
-
Open the battery compartment (see
chapter on changing the battery), and
check to determine whether the battery is
installed. Install the battery if necessary.
-
Charge battery of the BT 200 via char-
ging shell (approx. 4 hours).
U
Attention!
The battery is always delivered uncharged.
The charging shell is not included and must
be ordered separately.
-
Measuring cannot be performed during
the charging procedure.