7.6
Power on
After installation or inspection, carry out a test run:
1. Start up the machine without a load. To do this, close the circuit breaker and do not, if at
all possible, switch off prematurely. Check whether it is running smoothly.
Maximum number of permissible consecutive starts for machines on the power supply:
Three cold / two warm
The start conditions for converter machines can be found in the catalog.
Switching the machine off again while it is starting up and still running at slow speed should
be kept to a bare minimum, for example for checking the direction of rotation or for checking
in general. Allow the machine to run down before switching it on again.
2. Continue to observe the machine for a while in no-load operation.
3. If it runs perfectly, connect a load.
– Check whether it is running smoothly.
– Read the values for voltage, current, and output and log them.
– If possible, read and log the corresponding values for the working machine.
– If this is possible using the available measuring equipment, check the bearing and stator
winding temperatures until they have reached steady-state values.
– Check the machine for noise or vibrations on the bearings or bearing shields as it runs.
4. In case of uneven running or abnormal noise, switch off the machine. As the machine runs
down, identify the cause.
– If the mechanical operation improves immediately after the machine is switched off, then
the cause is magnetic or electrical.
– If the mechanical operation does not improve immediately after switching the machine
off, then the cause is mechanical. For example, this can be caused by imbalance in the
electrical machine or the driven load, inadequate alignment of the machine set,
operation of the machine at the system resonance point (system = motor, base frame,
foundation etc.).
NOTICE
Serious damage to the machine
The vibration values encountered during operation must be satisfied in accordance with DIN
ISO 10816-3, otherwise the machine could be damaged or destroyed.
During operation, observe the vibration values in accordance with DIN ISO 10816‑3.
7.7
De-energizing
● If the controller does not do this automatically, switch on any anti-condensation heating
during stoppages. This will avoid the formation of condensation.
● Do not switch on the anti-condensation heating until at least one hour after the motor has
been switched off. This prevents damage to the winding insulation.
Start-up
7.7 De-energizing
SIMOTICS TN Series N-compact 1LA8
Operating Instructions 05/2014
87
Содержание 1LA8
Страница 2: ...23 05 2014 10 18 V8 00 ...
Страница 12: ...Table of contents SIMOTICS TN Series N compact 1LA8 12 Operating Instructions 05 2014 ...
Страница 14: ...Introduction 1 1 About these instructions SIMOTICS TN Series N compact 1LA8 14 Operating Instructions 05 2014 ...
Страница 60: ...Assembly 5 3 Installing the machine SIMOTICS TN Series N compact 1LA8 60 Operating Instructions 05 2014 ...
Страница 88: ...Start up 7 7 De energizing SIMOTICS TN Series N compact 1LA8 88 Operating Instructions 05 2014 ...
Страница 100: ...Operation 8 11 faults SIMOTICS TN Series N compact 1LA8 100 Operating Instructions 05 2014 ...
Страница 173: ...AC Declaration of conformity 1LA8 area 22 AA KE NSR _1LA8_1PQ8_1PP8_1LP8 ...