COMMISSIONING
6
63
8023732/2018-09-10|SICK
Subject to change without notice
O R I G I N A L O P E R A T I N G I N S T R U C T I O N S | AOS301-WWD
6.7
Checking measurement operation is working properly
A test run after commissioning must make sure that the system components are working
correctly and that they are delivering plausible measurement results.
The test run can only be performed if the site configuration process has been successfully
completed and all of the system functions and system components in the navigation tree
have a green circle next to them.
6.7.1
Displaying vehicles with measured values
Whenever TEMS Manager is connected to the TEMS Recorder, the
Normal-way driver
objects
and
Wrong-way driver objects
working ranges contain a table of the last 200
vehicles recorded. These are listed in chronological order.
Among other things, the display shows the time of recording, the direction of travel, the
monitored lane, the number of single measurements and the length and width of the
trajectory.
▸
Defining the number of vehicles displayed per page
▸
Filter vehicle list via the search field.
▸
Display or hide columns using the tool icon.
Editing display