1. Ensure your base is firm and
absolutely level. 
2. Lay floor panel down onto your
base. 
3. Pre drill holes at top, middle and
bottom of each panel. 

4. Place back panel and a side
panel at one corner of the floor 
ensuring the cladding has overhung 
the floor.  Secure together from the 
inside using 3 x 60 mm screws. 
THE SIDE PANELS EXTEND 
FROM FLOOR EDGE TO FLOOR 
EDGE. THE PANELS AT THE 
BACK AND FRONT SCREW TO 
AND FIT INSIDE THE SIDE  
PANELS.  
5. Place other side panel in position
and secure to back panel from the 
inside using 3 x 60 mm screws. 
6. Place wing panel in position at
the front and secure to side panel 
from the inside using 3 x 60 mm 
screws. 

1. Place one gable on top of back
panel ensuring the outer edges are 
flush with shiplap of side panels.  
Secure from underneath panel  
framework into gable using 2 x 60 
mm screws. 

2. Place other gable in position at
the front. Secure half of the gable 

from the inside from underneath 
wing panel framework into gable 
using 1 x 60 mm screw. Secure 
other end of gable from the outside 
through gable framework into side 
panel framework. 

1. Position door stop strip at the top
of the door aperture flush with the 
front of framework. Secure using 3 
x 40 mm nails. 
2. Secure the cover strip which
goes at the corner of the building 
where the door is to be placed  
using 3 x 40 mm nails. 

 

3. Lay door down onto a flat level
surface. Check which side of the 
door the hinges are to be fitted. The 
side where the bracing does not 
extend to the edge of the boarding 
is the hinge side. 
4. The hinges are to be fitted onto
the boarding which covers each 
horizontal door bracing. Make sure 
the movable part of the hinge over-
hangs the edge of the door. Secure 
using 4 x 25 mm screws per hinge. 

5. Place door into aperture, check
door is square and even all the way 
round and secure in place using 3 x 
25 mm screws per hinge. 

6. Pre drill two holes in pad bolt
fixing block. Place block to the top 
side of the central bracing frame-
work on the back of the door and 
secure using 2 x 60 mm screws.

 

1. Place one roof panel onto piece
of felt allowing approx. 45 mm over-
hang on all sides. Fold felt over 
onto roof panel and secure  
together using felt nails spaced at 
approx. 100 mm intervals  

2. Place other roof panel onto the
remaining piece of felt, allowing an 
overhang of approx. 45 mm on 
three sides and an approx. over-
hang of 200 mm on the forth side. 
Fold felt over onto roof panel,  
except for the side with the approx. 
200 mm overhang, and secure in 
place using felt nails. 

3. Place roof panel, with felt on all
sides fixed, into position flush with 
front and back of building. Secure 
through roof panel into gable frame-
work using 3 x long felt nails per 
gable edge and 2 x long felt nails 
into side wall. 
4. Repeat for other roof panel, en-
suring that the 200 mm felt over-
hang goes over the ridge of the 
building to overlap felt of the other 
panel. Secure panel as before and 
secure overlapping felt using felt 
nails. 

1. Secure wall panels to the floor on
the inside of the building using 2 x 
60 mm screws for back and side 
panels and 1 x 60 mm screw for 
wing panel, preferably into floor 
bearer.

 

1. Secure remaining three cover
strips in position where the panels 
meet using 3 x 40 mm nails per 
strip. 

1. Secure the four fascia boards to
gable ends using 3 x 40 mm nails 
per fascia piece. 
2. Secure diamond on top of and in
the centre of front fascia using 2 x 
40 mm nails.

 

1. Place pad bolt on the outside of
the door directly over the horizontal 
brace. Ensure the edge is flush with 
the edge of the door. Secure to 
door using 4 x 25 mm screws using 
the round holes only. 
2. Place pad bolt housing in position
to accommodate the pad bolt.  
Secure using 2 x 25 mm screws 
using the round holes only. 

A  Wall Assembly 

B  Gable Assembly 

C  Door Assembly 

D  Roof Assembly 

E  Secure Walls to Floor 

F  Cover Strips 

G  Fascia & Diamond 

H  Bolt Assembly 

1

 Check and ensure that no raised grain or splinters 

are evident on timber components. Sand down 
any raised grain or splinters using fine grade 
sandpaper.   

          

2

 Check that all screw, nail and pin heads are    

properly tapped home and are not proud of the 
timber surface.  

3

 Check and ensure that no screws, nails or pins 

   protrude through any panel. 

4 Check and ensure that all parts are properly  

secured against reasonable force.       

5

 Do not apply decorative wood finish/treatments to 

wet or damp timber. Please observe the instruc-
tions of the wood finish/treatment manufacturer. 

Assembly Completion Checklist

 