INSTALLATION | Installation of SPLC models
Doc #OI0003 Part #004122 Rev 04 2010
|
49
Gland Plate Fitout
To maintain the IP rating and safety approval of the SP PRO, all gland plate holes must be completely filled.
For any unused holes, plug these with the supplied blanking plugs. If the plug is metal; once installed from
the underside of the gland plate, ensure that it is secured in place by bending all of the inner fingers tabs over
flush.
Initial Start up Procedure
Before turning on the SP PRO double check all connections, paying particular attention to correct polarity.
Give each cable a gentle tug to ensure it is securely fitted. If satisfied everything is well, attach the terminal
cover plate.
Protective cover MUST be installed on Expansion card.
Switch battery feed on to the battery sense/pre charge and the main battery connection. Close Battery Sense/
Pre charge switch - under the expansion card - and wait until all LEDs are lit and stable.
DC Circuit Breaker will not close until pre charge is complete.
Close DC Circuit Breaker.
Press output mode button (long press > 1 second) once, AC Load LED will be steady blue.
You can now start to use your SP PRO by turning on both AC Source and AC Load circuit breakers.
Replace top cover and tighten thumb screws.
To maintain IP rating, thumb screws must be tightened enough that they require a screw driver to
loosen.
Labelling
Regulations mandate the application of warning and control labels to the various circuit breakers, isolators and
switch boards in the installation.
The SP PRO behaves like a UPS and will continue to provide power to the load upon interruption of mains
supply. Warning signs must indicate which circuits or switchboards operate in this manner. For further
information see AS4777.1 section 5.6 Additional Requirements for UPS systems.