7. I N S TA L L T H E FI R S T M O D U LE

Apply the Rapid 16 end clamps (at the top and at the botto m ) to the module and tighten, Screw s
M8 (T40).

8 . I NS TA L L FI R S T M O D U LE

Apply the next module.

Tighten the middle clamps (at the botto m and at the top) between the modules with Screws M8
(T40)

P re-assemble the other middle clamp on the free module side.

Connec t the module cable acc ording to the plan.

Repeat steps up to the last module in the row.

Place the module c enter clamp on the module; do not tighten.

Connec t the module cable acc ording to the plan.

6 . A P P LY T H E F I R S T M O D U L E

Click Rapid 16 end clamps into place at the edge of the module field and position them. Also click
the Rapid 16 middle clamp into place at a genero u s distance so that the module can be inserted
between the clamps.

Place the module on the FixZ S ystem Rail 18 and align it with the upper edge using the pre-
attached Rapid 16 clamps. Pay attention to the alignment of the module row.

Torque Value for Rapid16 clamps = 15 N.M/11 FT-LBS
(available in 50 or 100mm lengths)

FIXGRID EAST-WEST   I   V1  I   INSTALLATION MANUAL   I   

12-2020 SCHLETTER NA Inc.  I  SUBJECT TO CHANGE 

WITHOUT NOTICE

8

Содержание FixGrid East-West

Страница 1: ...F i x G r i d E a s t W e s t short side clamping F i x G r i d E a s t W e s t long side clamping INSTALLATION MANUAL...

Страница 2: ...med by qualified personnel Observe the safety regulations of the PV module manufacturer Risk of falling There is a risk of falling when working on the roof and when climbing up and down Is it imperati...

Страница 3: ...ified lightning protection company is necessary Whether or not the lightning protection requirements change as a result of the installation also has to be determined Due to static reasons the installa...

Страница 4: ...base rail length can be selected from the six standard lengths 2150 2650 3150 4200 6000 6300 mm and combined with each other The base rails can be connected with the internal connector Item No 129078...

Страница 5: ...s The base rail length can be selected from the six standard lengths 2150 2650 3150 4200 6000 6300 mm and combined with each other The base rails can be connected with the internal connector Item No 1...

Страница 6: ...r the distance has to be dimensioned on the basis of the amount of precipitation on site The installation distances of the surface protection mats below the base rail result from the chosen installati...

Страница 7: ...e of 100 mm Load introduction on large area for high loads and or soft subsoil with low permissible surface pressure Also suitable for transversely draining roof water The permissible surface pressure...

Страница 8: ...odule do not tighten Connect the module cable according to the plan 6 APPLY THE FIRST MODULE Click Rapid 16 end clamps into place at the edge of the module field and position them Also click the Rapid...

Страница 9: ...Ballasting with 100 mm wide concrete blocks on the base rails see Detail A Ballasting with additional trough see Detail B Ballasting with additional ballast shafts see Detail C Ballasting from the co...

Страница 10: ...stand on the base rails All other trays are turned 180 degrees recesses on the left from right to left The tray always lies with the side of the slots at the bottom and in the base rail with a positiv...

Страница 11: ...E TWO MODULES OF THE EAST WEST CONFIGURATION FIXGRID EAST WEST I V1 I INSTALLATION MANUAL I 12 2020 SCHLETTER NA Inc I SUBJECT TO CHANGE WITHOUT NOTICE 11 BALLAST EXAMPLES FIXGRID 10 PER ONE OF THE TW...

Страница 12: ...HE TWO MODULES OF THE EAST WEST CONFIGURATION FIXGRID EAST WEST I V1 I INSTALLATION MANUAL I 12 2020 SCHLETTER NA Inc I SUBJECT TO CHANGE WITHOUT NOTICE 12 BALLAST EXAMPLES FIXGRID 5 PER ONE OF THE TW...

Страница 13: ...ER TWO MODULES OF THE EAST WEST CONFIGURATION FIXGRID EAST WEST I V1 I INSTALLATION MANUAL I 12 2020 SCHLETTER NA Inc I SUBJECT TO CHANGE WITHOUT NOTICE 13 BALLAST EXAMPLES FIXGRID 5 PER TWO MODULES O...

Страница 14: ...part and continues via the screw the assembly claw the module suport and the turn in connector to the basic profile The external bonding path must be specified by the Installer COMPONENTS RECOMMENDED...

Страница 15: ...onal Electrical Code including NEC 250 Grounding and Bonding and NEC 690 Solar Photovoltaic Systems and Installation shall be in accordance with CSA C22 1 Safety Standard for Electrical Installations...

Страница 16: ...eral amount of conductor compound in wireway of ground lug 5 Install ground conductor in lug and torque wire screw to the following 6 AWG 35 in lbs 8 AWG 25 in lbs 10 14 AWG 20 in lbs Flat washer and...

Страница 17: ...t a PV module complying with UL 1703 only when the specific module has been evaluated for grounding and or mounting in compliance with the included instructions O vercurrent Protection Device groundin...

Страница 18: ...rking properly WARNING The PV System must be shut down first if it needs any electrical maintenance Improper maintenance may cause lethal electric shocks or burns Fire Test FixGrid racking system meet...

Страница 19: ...00 kPa RAPID 16 shear strength kN clamp INFORMATION O N TENSILE OR SHEAR STRENGT H Rapid 16 module clamps according Z 14 4 631 available in 50 or 100mm lengths SHEAR Load direction TENSILE Profile FT...

Страница 20: ...W MB AG CS3W CS3U PB AG CS3U P CS3U MS CS3U MB AG CS3U CS3L P CS3L MS CS3L CS3K PB AG CS3K P CS3K MS CS3K MB AG CS3K CS1Y MS CS1U MS CS1K MS CS1H MS ET M660 290 285 280 275 270 WW WB ET M672 340 335 3...

Страница 21: ...3 Q PEAK DUO L G6 Q PEAK DUO L G6 1 Q PEAK DUO L G6 2 Q PEAK DUO L G6 3 Q PEAK DUO L G6 4 Q PEAK DUO L G6 5 Q PEAK DUO L G6 6 Q PEAK DUO L G6 7 Q PEAK DUO L G7 Q PEAK DUO L G7 1 Q PEAK DUO L G7 2 Q PE...

Страница 22: ...265PP 60 JKM270P 60 V JKM275P 60 JKM275PP 60 V JKM320P 72 V JKM330P 72 JKM330PP 72 V JKM390 395 400 405 410M 72HL V JKMxxxM 60HBL JKMxxxM 72HL TV JKMxxxM 7RL3 TV JKMxxxM 7RL3 V LG LGxxxN1C A5 LGxxxN1C...

Страница 23: ...0 290 MONO BLACK 5 busbar Sunmodule Plus SW 280 295 MONO Sunmodule Plus SW 285 300 MONO 5 busbar Sunmodule Pro Series SW 260 POLY WOB Sunmodule Protect SW 275 280 MONO BLACK Sunmodule SW 100 POLY RGP...

Страница 24: ...M DE14A TSM DD14A TSM PD05 TSM PD05 05 TSM PD05 08 TSM xxx DD05A 05 II TSM xxx PD05 08 TSM xxx PD05 10 TSM PD14 TSM PE14 TSM PEG14 TSM PEG40 07 TSM PEG5 TSM PEG5 07 TSM DD06M 05 II TSM DE06H TSM DE06M...

Страница 25: ...ZXM6 H120 xxx_M ZXM6 H144 xxx_M ZXM6 HLD120 xxx_M ZXM6 HLD144 xxx_M ZXM6 HLDD144 xxx_M ZXM6 LD60 xxx_M ZXM6 LD72 xxx_M ZXM6 LDD72 xxx_M ZXM6 NH120 xxx_M ZXM6 NH144 xxx_M ZXM6 NHLD120 xxx_M ZXM6 NHLD1...

Страница 26: ...SCHLETTER NA INC 5200 77 Center Drive Suite 250 Charlotte NC 28217 Phone 1 704 595 4200 Fax 1 704 595 5210 CANADA Phone 1 519 946 3800 rooftopNA schletter group com www schletter group com 26...

Отзывы: