7.3. BURNING 

 

 

During normal  exploitation  of boiler  burning  process  is based on  periodic refueling and 
raking a grate by  moving the  arm  of  mobile  grate  mechanism  (pos.  11* ). Single  load  of  
basic    fuel    is    sufficient    for    6  hours    of    boiler    operation    at    rated    power.    With    lower  
capacity   the  period   of  slow   burning   (time    gap between refueling)  may  be elongated to 
several hours. 
When  refueling  the controller should be switched  off,  then  slowly  open  the  fuel  charge 
door,  introduce  another  load  of  fuel,  close  the  door  and  switch  on  the  controller  again.  In  
emergency situations (blackout), open ash  box  door,  switch the controller  off the mains, in 
order    to  prevent    ventilator    from    working    once  electric    power    is    resumed.    Otherwise  
fumes    may    be    blown    out  into  boiler  room.  In    the    central  heating    installation    heating  
requirement  is   changing   along  with  outdoor   conditions, e.g. daytime  and  temperature.  
Temperature  of  water  leaving  out  the  boiler  depends  also  on  thermal characteristic of 
building,  e.g.  construction  materials,  in  particular  the  insulation  one. With    boilers    of   SAS  
NWT  type,  regulation  of  combustion  intensity  and  heat  capacity,  depending  on weather 
conditions, is done by microprocessor controller.  The  controller ensures  optimal combustion 
process,  by  regulating fan  and  circulation pump work.    Fan’s  rotational speed depends on  
measured temperature  and  parameters  setting. Once fire up process is finished,  and  boiler  
riches  required  temperature,  the  controller  keeps  it  constant.    If  boiler’s temperature is 
lower  than    set,    rotation    speed    of    fan    is    increased,  if    it    is    higher,    scavenges    of    the 
boiler are only performed.  

 

7.4.CLEANING THE BOILER  

 

In order to use fuel in the safe manner, and to get declared boiler’s power and heat efficiency, 
keeping  adequate  cleanliness  of  combustion  chamber  and  convection  channels  is 
indispensable. 
As  far as  furnace chamber  of the boiler is considered,  special attention should be paid when 
removing ash and slag  from between  grate orifices and  chamber’s walls.  Such  a  cleaning  
should  be exercised prior  each boiler’s  fire up  process, but not less than    after  150÷260  
of  boiler’s  continuous    work.  Cleaning    of    convection    channels,    with    volatile    ashes  
residues,  should  be  performed  every  3÷7 days,  depending on quality  of burned fuel.  The 
cleaning operation is done through washout holes indicated  on  the  drawing  (p.  13,    pos.    
15,    17).    Once  cleaning  is  finished,  those  wholes should be sealed  tightly. 
Cleaning  the  chimney  duct  is not less important. In  case of low  temperatures  in boiler in 
the longer time, it is necessary to “heat”   the boiler periodically (at  least once a week)

 

(burning-out  in  temperature  70÷80°C).    This  is  important  for  extending  the  durability  of 
boiler.

 

 

7.5. END THE HEATINHG SEASON  

 

 

Once  heating  season is finished,  or  in  other  cases  of  scheduled  stops,  wait  the  fuel  to  
be  completely  burned  out.  Once  boiler  is  out  and  cooled  down,  remove  from  the  furnace  all 
remains  of  burned  fuel  and  apply    cleaning    and    conservation    of    the    entire    boiler.  Pay  
special  attention  to  lubricate  inner partitions  and  movable elements with oil.  
 

*Does not apply to boilers of power above  36kW

 

Содержание NWT

Страница 1: ...L A R S K I 28 100 Busko Zdr j Owczary ul Przemys owa 3 Phone 48 41 378 46 19 Fax 48 41 370 83 10 TECHNICAL START UP DOCUMENTATION of water boiler s for heating installations SAS NWT type adopted for...

Страница 2: ...r to a heating installation 8 6 5 Connecting boilers to electrical installation 9 7 Operation and installation guidelines 9 7 1 Filing with water 9 7 2 Boiler s firing up 10 Table technical exploitati...

Страница 3: ...3...

Страница 4: ...4...

Страница 5: ...ler is 0 30 0 55 mbar depending on boiler s power These boilers may also work in hot water installations utilizing a heat exchanger Boiler s selection for building heating should be based on heat bala...

Страница 6: ...neral wool which fill the space between the heat exchanger and boilers casing pos 1 Coal heating boilers of SAS NWT type are equipped with a controller and blow in fan Boilers work based on the proces...

Страница 7: ...cal Start Up Documentation 6 1 REQUIREMENTS FOR BOILER ROOM The boiler room where the heating boiler for central heating installation shall be installed must conform the requirements of detailed regul...

Страница 8: ...on detailed regulations being in force in the country of destination Assuming that it is not possible to achieve such parameters for chimney and chimney draught problems are experienced resulting in i...

Страница 9: ...r temperature below 55 C then the boiler should be connected to the heating installation equipped with three or four pass valve protecting it against low temperature corrosion 6 5 CONNECTING BOILER TO...

Страница 10: ...pieces of paper and wood Then thin layer of coal is applied Once a coal is glowing the ash box and furnace door must be closed Open fuel charge door and fill the combustion chamber with fuel reaching...

Страница 11: ...g pressure bar 1 5 11 Maximal allowable working temp C 85 12 Recommended heating water working temp C 60 80 13 Minimal return water temp C 55 14 Power supply V Hz 15 Power consumption 16 Dimensions A...

Страница 12: ...735 785 835 885 885 935 985 985 1035 H 1500 1560 1560 1560 1610 1635 1685 1735 1735 1780 1830 1830 1870 H1 1470 1530 1530 1530 1580 1605 C 1655 C 1705 C 1705 C 1750 C 1800 C 1800 C 1840 C H2 350 300 3...

Страница 13: ...r jacket 8 glow prevention grid 13 smoke conduit cleaning hole 18 blowdown connection 23 temperature regulator controller 4 furnace chamber 9 water grates 14 smoke throttle 19 hot water connector pipe...

Страница 14: ...tion connector pipe 3 water jacket 8 water grate 13 temperature sensor well 18 smoke conduit cleaning hole 23 blowdown connection 4 return water connector pipe 9 furnace chamber 14 hot water connector...

Страница 15: ...troller keeps it constant If boiler s temperature is lower than set rotation speed of fan is increased if it is higher scavenges of the boiler are only performed 7 4 CLEANING THE BOILER In order to us...

Страница 16: ...fire up a boiler by use of petrol kerosene solvents explosion may occur causing he operator to be burned in case of installation malfunction and lacking water in a boiler do not fill it in if boiler...

Страница 17: ...r s start up and after each standby heat the boiler e g burn it up to 70 C and keep that temperature for several hours Hitting shooting in boiler air in the heating installation and boiler due to impr...

Страница 18: ...ng a boiler to a heating installation make check if all boiler s components are in good working condition and that the boiler is fully equipped NOTE Boilers need to be transported in the vertical posi...

Страница 19: ...lized by manufacturer is only possible based o expert opinion that repair is not workable 10 If the advertiser does not allow double warranty repairs despite the willingness of the guarantor to comply...

Страница 20: ...tation shall be addressed ZAK AD METALOWO KOTLARSKI Owczary ul Przemys owa 3 28 100 Busko Zdr j Tel 4841 378 46 19 Fax 4841 370 83 10 http www sas busko pl e mail biuro sas busko pl serwis sas busko p...

Страница 21: ...21 SERVICE REPAIRS...

Страница 22: ...mperature boiler of SAS NWT type installed and operated in pursuance of Technical Start Up Documentation Boiler no Heating capacity Heated surface Year of manufacture Manufacturer signature and stamp...

Отзывы: