    S&C Instruction Sheet 716-502

Installing the Switch Operator

STEP 8. 

Loosen  the  ½  -13 

×

 1-¼  -inch galvanized steel cap 

screws, fl at washers, and nuts attaching the bottom 
plates to the underside of the high-speed base. 
Remove the plates and place them and their 
hardware aside on a clean surface. See Figure 6. 

Remove the 

¾

 

 

-inch stainless steel pin and cotter 

pin from the interphase drive lever enclosed in the 
high-speed base. See Figure 7. Retain the pin and 
cotter pin for re-use in Step 14 on page 18.

 CAUTION

Do not attempt to set the operator upright 
by slinging to the skid.
 The skid is not 
designed to carry the weight of the switch 
operator . Damage to the operator and minor 
personal injury may result .

STEP 9. 

Wrap a lifting sling around the stored-energy 
housing of the operator, as shown in Figure 8 (left). 

Now carefully raise the operator to the upright 
position so that it rests on its base skid, as shown 
in Figure 8 (right). 

 CAUTION

DO NOT remove the lifting sling around 
the stored-energy housing after raising the 
operator . The operator is top-heavy and must 
be adequately supported until it is attached to 
the high-speed base . Damage to the operator 
may result .

Remove the skid and bracing that runs the 

length of the operator, the stored-energy housing, 
and the operator support tube. See Figure 8. Also 
remove the protective cover and packing on top of 
the operator support tube as well as the packing on 
the operator enclosure louvers. See Figure 8,  and 
Figure 9 on page 15.

STEP 10. 

Lift and install the operator as follows:

 CAUTION

Be careful not to damage the uni-ball coupling 
on the operator connecting link during hoisting 
and attachment of the operator . The uni-
ball coupling cannot be replaced in the field . 
Damage will necessitate returning the operator 
for replacement .

(a)  Reposition the lifting sling around the front of the 

stored-energy housing and wrap another lifting 
sling around the back of the stored-energy housing, 
as shown in Figure 9 on page 15. Make sure the 
operator door faces the same way as the switch-
position indicator on the high-speed base.

Figure 7. Remove the ¾-inch stainless-steel pin and cotter pin 
from the interphase drive lever inside the high-speed base.  

Pin and cotter pin

Figure 8.  (Left and Right) Typical shipment of Series 2000 Opera-
tor. Wrap lifting slings around stored-energy housing to raise the 
operator to the upright position. 

Stored-energy 
housing

Packing

Figure 6.  Remove bottom plates from high-speed base.

Bottom plate

Installation

Содержание 2000 series

Страница 1: ...gh Speed Base 12 Installing the Switch Operator 14 Installing the Pole Units 15 Connecting the Pole Units to the High Speed Power Train 17 Connecting the Operator to the High Speed Power Train 18 Conn...

Страница 2: ...ages 4 through 7 Retain this Instruction Sheet This instruction sheet is a permanent part of your S C Series 2000 Circuit Switcher Model 2040 These instructions should be stored in the Series 2000 Swi...

Страница 3: ...tored installed operated inspected and main tained in accordance with recommendations of the seller and standard industry practice to correct the nonconformity either by repairing any damaged or defec...

Страница 4: ...es or requirements that can result in product or property damage if instructions are not followed Following Safety Instructions If you do not understand any portion of this instruction sheet and need...

Страница 5: ...Location of Safety and Instruction Labels and Tags Q A G F E D C B P K L J H M N Safety Information S C Instruction Sheet 716 502 5...

Страница 6: ...2 115 V 60 Hz G 5948 3 K Instruction Instructions for Fuse Slugs G 5939 L CAUTION Do not apply control voltage to this device or insert G 5959 M CAUTION Do not apply control voltage to this device or...

Страница 7: ...otection and flash clothing in accordance with safe operating procedures and rules SAFETY LABELS AND TAGS Do not remove or obscure any of the DANGER WARNING CAUTION or NOTICE labels and tags Remove ta...

Страница 8: ...t should include the following items as shown in Figures 1 and 2 on pages 10 and 11 CAUTION DO NOT mix components from different installations The Series 2000 Circuit Switcher is completely factory as...

Страница 9: ...ntrol power to the switch operator when storing it outdoors The switch operator is equipped with a space heater that must be energized during storage to prevent condensation and corrosion within the o...

Страница 10: ...nterrupter power train enclosed in steel sheathed box type high speed base Single gap SF6 puffer type Interrupter Pressure relief device and low gas pressure indicator not visble Insulating support co...

Страница 11: ...themountingpedestals to the high speed base Cut the straps binding the container of operating mechanism components and hardware and the straps binding the pole units Remove any wood bracing between th...

Страница 12: ...nd flatwashers Looselysecureaflatwasherandnutto each anchor bolt above the pedestal base See Figure 3 Remove the lifting slings and eyebolts e Adjust the lower set of anchor bolt nuts to plumb and lev...

Страница 13: ...cate the bolts to facilitate tightening Use a level to verify the high speed base is horizontal both lengthwise and sideways Adjust the lower set of anchor bolt nuts at the pedestals to achieve level...

Страница 14: ...e the skid and bracing that runs the length of the operator the stored energy housing and the operator support tube See Figure 8 Also remove the protective cover and packing on top of the operator sup...

Страница 15: ...le units are numbered Pole 1 Pole 2 and Pole 3 Make sure to install the pole units in the order marked on the catalog drawing Please note that the pole numbers do not have to correspond with your syst...

Страница 16: ...unit a few feet then remove the two 13 1 inch hex head galvanized steel cap screws flat washers and hex nuts that attach the shipping bracket to the bottom of the pole unit base The shipping bracket...

Страница 17: ...drive in the high speed base as follows a Remove the six 5 16 18 inch hex head stainless steel cap screws used to attach the access cover to thesideofthetransitionbox SeeFigure11 Remove the cover and...

Страница 18: ...rted lock it in place with its retainer g Remove and discard the 5 16 18 x 2 inch hex head stainless steel screw spacer and stop bracket marked with a black yellow striped label shown in Figure 12 on...

Страница 19: ...gth of the container b Remove and discard the 16 inch and two 16 1 inch zinc plated hex head cap screws and flat washers that attach the upper container half to the coupling end casting of the interru...

Страница 20: ...n the conduit entrance plate in the bottom of the operator enclosure See Figure 16 Removetheplateandcutoutthenecessaryopening Apply sealant and replace the plate Make up and connect the entrance fitti...

Страница 21: ...closing circuit conductors must be adequately sized for the ampacities indicated on the wiring diagram NOTICE Trip circuit conductors and motor and closing circuit conductors must be adequately sized...

Страница 22: ...ee Figure 12 on page 17 If the optional remote gas density monitor is present catalog number suffix R make sure connections are made according to Instruction Sheet 716 530 b At each interrupter make s...

Страница 23: ...ure 24 on page 25 e Make sure all other pinned connections have been made and all bolted connections have been securely tightened STEP 21 Replace the access cover on the side of each transition box an...

Страница 24: ...eplaced with the slugs furnished This practice is recommended for increased reliability because low voltage fuses can be damaged by the repeated inrush current experienced during normal opening operat...

Страница 25: ...lace Push the surge support if present back into place Motor contactors should be fully seated if present back into place Motor contactors should be fully seated Figure 24 Check that all optional ice...

Страница 26: ...ns in the mechanism downward which can be seen in the DIS CHARGED indicator window inside the operator See Figure 26 on page 27 The switch position indicator on the high speed base will move to the Op...

Страница 27: ...e 25 on page 26 If the position indicating lamp option has been specified and operator control voltage is available the green lamp will light If operator control voltage is available the motor driven...

Страница 28: ...errupter The remote gas density monitor transmits updated measurements approximately once per hour The remote gas density monitor has three available alarm contacts The system provides both local and...

Отзывы: