Site Preparation
Before installing an Ubigate iBG2006, ensure that the site conditions comply
with the following requirements and that the mounting equipment, tools, and
cables are available at the designated site.
For safety, Ubigate iBG2006 is intended to be installed in a restricted access
location by a service person.
See Required Tools and Materials for information about tools and materials
required for installation.
Environment
Site location is important for the proper operation of Ubigate iBG2006.
Place the unit in a clean and dry environment with adequate air circulation.
Allow two to three feet additional clearance around the router for access to the
cable connectors on the front and rear panels.
The selected installation site must meet basic environmental requirements.
The following figure shows a top view of the path of cooling air through the
chassis. Clearance must be maintained near the air intake and exhaust vents to
prevent overtemperature conditions, which could result in router failure or
performance degradation.
Figure 2.1 Air flow of the Ubigate iBG2006
Содержание Ubigate iBG2006
Страница 1: ......
Страница 14: ...INTRODUCTION XII SAMSUNG Electronics Co Ltd This page is intentionally left blank ...
Страница 26: ...TABLE OF CONTENTS XXIV SAMSUNG Electronics Co Ltd This page is intentionally left blank ...
Страница 96: ...ANNEX A Specifications A 4 SAMSUNG Electronics Co Ltd This page is intentionally left blank ...
Страница 106: ...EQNA 000051 Ed 01 ...