Mounting and start-up
V
Δp
•
–+
+–
M
Fig. 3:
Installation example
M
DN
min.
b x DN
min.
3 x DN
min.
3 x DN
min.
a x DN
Control
line
State of process medium
Valve conditions
Inlet length a
Outlet length b
Liquid
w < 2
m
/
s
2
4
Fig. 4:
Control line connection and how the pipeline is routed
Pipeline routing
The inlet and outlet lengths vary depending
on several variables and process conditions
and are intended as recommendations. Con-
tact SAMSON if the lengths are significantly
shorter than the recommended lengths.
To ensure that the regulator functions proper-
ly, proceed as follows:
Î
Observe the inlet and outlet lengths (see
Fig. 4). Contact SAMSON if the regula
-
tor conditions or state of the medium
process deviate.