9
15. You are now ready to lift the hoist into place.
Warning: When setting up your hoist please take note of all
overhead obstructions and/or electrical wires. Select a
location that is free of traffic and pedestrians.
16. Lay the assembled hoist along side the wall where the hoist is to be used.
17. Drop and end of rope from the roof to the ground. Tie the end of the top rung of
the last section and use the rope to lift the top of the hoist to the roof. While the
hoist is being lifted, one or two people on the ground should brace the feet of
the hoist and walk the hoist up until it is vertical.
18. Once the hoist is vertical, lean it up against the building.
19. Place Hoist against building at the proper safe angle. Use the chart below, as a
guide to determine the angle of incline of the Hoist for the length of the Hoist to
be assembled. Secure track to roof with a rope to prevent hoist from sliding
along roof. Tie rope to a rung or the peak NOT to side rails of track. Tying to
side rails will stop carriage from going up and down.
Chart A
Approx.
Height to Maximum Horizontal Hoist
Bearing Point Distance Length
“A” “B” “C”
13 ft. 3.ft. 4 inches 15ft
Base + 8’ + 4’*
21 ft. 5ft. 4 inches 23ft.
Base + (2)-8’ + 4’
25 ft. 6ft. 3 inches 27ft.
Base + (3) – 8’
Содержание VH-300
Страница 10: ...8...