设备安装
Install the switch
安装前准备
Installation tools
−
安装到桌面:防静电手环或防静电手套
Mounting on the desktop: ESD bracelet or gloves
−
安装到
19
英寸标准机架:螺丝刀、螺钉、防静电手环或防静电手套
Mounting to a standard 19-inch rack: screwdriver, screws, ESD bracelet or gloves
−
安装到墙面:记号笔、冲击钻、橡胶锤、梯子、螺丝刀、螺钉、膨胀螺管、防静电手环
或防静电手套
Mounting to the wall: marker, hammer drill, rubber hammer, ladder, screwdriver,
screws, expansion bolts, ESD bracelet or gloves
安装到桌面
Mounting on the desktop
将脚垫粘贴在机壳底面四角对应的凹槽中,然后将交换机正面朝上放置于足够大且干净平稳
的桌面上。
Paste the footpad stickers to the corresponding four recesses on the bottom of the switch.
Then turn the switch upside down, and place it on a big enough, clean, stable and flat