MANDATORY OPTIONS WITH THE CLEAN FACING
When installing a Clean Facing (FO-CAMF-4) on your CHAMELEON, you MUST also install an Intake Duct (FO-
CID) to provide sufficient air to the unit along with at least one Gravity Vent Kit (FO-VCT) to provide an evacuation
path for all the heat. Neglecting to install either one of these options will result in overheating of the unit and may
put your safety at risk. Refer to each option's installation instructions for particular details.
Use only genuine RSF parts. The use of any substitutes will decertify the system and may put your safety at risk.
REFRACTORY BRICK INSTALLATION
The refractory bricks must be installed in proper sequence to allow them to fit in the firebox (see Figure 13).
Remove the door, if already installed, for easier access to the firebox. To remove any of the refractory bricks, just
follow the installation procedure in the reverse sequence.
1. Remove the secondary air tube at the top front of the firebox. To do so, unscrew the bracket located on the left
side of the tube.
2. Place the baffle (11.9.CT) above the other two tubes and ensure its proper orientation: narrow part towards the
rear and grooves towards the bottom (see Figure 13a).
3. Reinstall the first tube and screw it in place.
4. Insert the rear refractory brick in the firebox (11.3.CT), then the left side refractory brick (11.1.CT). See Figure
13b for the proper orientation.
5. Insert the refractory brick on the right side (11.2.CT) of the firebox but do not position it yet. Ensure that it is
resting firmly on the rear refractory brick as shown in Figure 13c.
6. Insert the arch refractory brick (11.8.CT) in the firebox as shown in Figure 13d.
7. Pivot the arch refractory brick until it is in a horizontal position (see Figure 13e) and then slide the right
refractory brick until it is in place. The arch refractory brick is supported by the two side refractory bricks.
8. Install the 2 bottom refractory bricks in the firebox (11.4.CT on the left and 11.5.CT on the right). To facilitate
the installation, remove the plug and insert the refractory bricks as shown in Figure 13f. First, slide the bottom
refractory brick below the square tube located at the front floor of the firebox. Then install the right refractory
brick in the same fashion. Replace the plug.
9. Finally, install the 2 front refractory bricks (11.6.CT on the left and 11.7.CT on the right) and the refractory plug
(11.10.C) as shown in Figure 13g.
CHAMELEON Owner's Manual
RSF Woodburning Fireplaces
15