Roth RADIANT PANEL SYSTEM Скачать руководство пользователя страница 7

5A. INSTALLATION INSTRUCTIONS 

5A.5 Pressure Test/Start-up 

 
After installation of the panel and tubing, but before laying the finished floor, you need to perform a pressure test. Fill the 
system with air or water and maintain a pressure of 2 to 3 times the working pressure of the system, about 25 to 50 psi (1.7 
to 3.4 bar) for 6 hours. Use a leak detection solution (if testing with air) to locate and repair any leaks in the system. A small 
leak can take a long time to register on a 60 psi (4 bar) gauge. 

Please note: If the system cannot be started up after the 

pressure test and there is a danger of freeze, you must use air or a glycol solution! Do not use plain water!

 Run the system at 

normal operating pressure at about 140°F (60°C) for 30 minutes to allow the tubing to relax and settle into the tracks. Noise can 
occur at this time but will reduce as the tubing settles. If the noise persists, locate the source and apply some silicone 
adhesive to the tubing at that location. After the start-up is complete, the finished flooring can be installed. 

5A.6 Sample Flooring Installations 

 

 

 

 

 

 

 

Tile/Stone:

 Roth recommends using a tile underlayment product in 

all

 ceramic tile installations. Underlayment should be 

secured and seams finished per manufacturer’s instructions. It is also a good idea to use plasticizer additives with the 
mastic and grout for more flexibility during operation of the heating system.  

Laminate Wood Flooring:

 Thin laminate flooring may require the use of an underlayment material to provide additional 

support above the tubing/grooves. This should be discussed with the flooring contractor during the planning phase. 

Carpeting/Vinyl Flooring:

 Never use untempered hardboard as an underlayment. Underlayment should be stable under 

the temperature and humidity conditions expected for your project. Untempered hardboard may swell with humidity. 

Hardwood: 

Nail strips may not be needed if the flooring contractor uses longer nails/staples. This should be discussed 

with the  flooring contractor prior to installation of the panel. Never use an asphalt impregnated paper, or any impregnated 
paper that can produce odors when exposed to heat between the panel and the hardwood. 

These are sample installations only! 

It is always important to coordinate any radiant heating with the flooring contractor prior to panel installation! 

The flooring contractor will then be able to incorporate any special requirements felt needed for the installation. 

5A 

Содержание RADIANT PANEL SYSTEM

Страница 1: ...5A RADIANT PANEL SYSTEM PLANNING INSTALLATION MANUAL rev ROTH HEATING SYSTEMS ...

Страница 2: ...It is ideal for retrofit systems but it s also great for new construction when you don t want the weight expense or water problems of lightweight concrete The efficient design of the system heavy gauge full face aluminum sheet on top and EPS insulating foam on the bottom focuses the heat exactly where you want it directly under the finished floor so that the system can run at the lowest temperatur...

Страница 3: ...ld locations We also recommend installing tubing in every track to achieve the best heat distribution Try to plan the pattern so that the Master Panels are aligned to allow the loop supply to run along the outer wall If installing a wood floor over the panel align the panel so the loops are running in the opposite direction of the wood flooring material In wet areas such as bathrooms etc where a w...

Страница 4: ...on in advance to be sure that you have the correct number of tracks when installing the tubing Transition and radius panels can be installed upside down as filler pieces When securing the panels to a wood subfloor we recommend using at least eight 8 countersunk screws spaced 12 30 cm apart and 6 15 cm from the edges When installing over concrete you can use countersunk concrete fasteners in the sa...

Страница 5: ...utting the panel remove any burrs When cutting the last master panel in the first row use the rest of the panel to start the next row This will provide staggered joints for the field panels After completion of the panel installation in an area use a vacuum to clean up thoroughly before installing the tubing Dirt and debris in the tracks can create noise when the system is put into operation 5A 3 ...

Страница 6: ...to fasten the tubes in the tracks Be sure to use a block when using a hammer or mallet to set the tubing to avoid denting the aluminum surface Follow the loop layout you have planned and connect the return tube to the manifold It is very important that the tubes are snapped down completely into the tracks When installing the tubing in the radius panels it is important to pull the tubing tightly ar...

Страница 7: ...layment product in all ceramic tile installations Underlayment should be secured and seams finished per manufacturer s instructions It is also a good idea to use plasticizer additives with the mastic and grout for more flexibility during operation of the heating system Laminate Wood Flooring Thin laminate flooring may require the use of an underlayment material to provide additional support above ...

Страница 8: ...o success are combinations of know how modern production sites and equipment latest production technologies and motivated personnel Roth Industries Inc 77 Circuit Drive North Kingstown RI 02852 Phone 401 267 9044 Fax 9048 http www Roth USA com E mail Roth USA Roth USA com Roth Canada 1607 rue de l Industrie Beloeil QC J3G 4S5 Phone 450 464 1329 Fax 7950 http www Roth Canada com E mail service roth...

Отзывы: