background image

 

65-2422RK-05 H

2

S Transmitter • 13

Start Up

This section describes procedures to start up the H

2

S transmitter and place the transmitter into 

normal operation.

Introducing Incoming Power

1. Complete the installation procedures described earlier in this manual.
2. Verify that the power wiring to the controller is correct and secure. Refer to the controller 

instruction manual.

3. Turn on or plug in the incoming power at the power source end, then turn on the controller.
4. Verify that the controller is on and operating properly. Refer to the controller instruction 

manual.

CAUTION:

Allow the transmitter to warm up for 5 minutes before you continue with the next 

section, “Setting the Zero Signal”.

Setting the Zero Signal

WARNING: Do not remove the sensor cap or junction box cover while the circuits are 

energized unless the area is determined to be non-hazardous. Keep the sensor 
cap and junction box cover tightly closed during operation.

NOTE:

If you can verify that the detector is in a fresh air environment (environment known to 
be of normal oxygen content and free of toxic and combustible gases), it is not 
necessary to apply zero air when verifying or setting the fresh air reading.

The procedure below describes applying zero emission air, usually called zero air, using a 
calibration kit that includes a calibration cup, calibration gas, sample tubing, and a fixed flow 
regulator with an on/off knob. RKI Instruments, Inc. recommends using a 0.5 LPM (liters per 
minute) fixed flow regulator.

1. Unscrew and remove the junction box cover from the junction box.

2. Set a voltmeter to measure in the millivolt (mV) range.
3. Plug the voltmeter leads into the test points on the amplifier. Plug the positive lead into the 

test point labeled 

TP+

; plug the negative lead into the test point labeled 

TP-

.

4. Screw the calibration cup onto the bottom of the detector.
5. Screw the regulator into the zero air calibration cylinder.

6. Use the sample tubing to connect the regulator to the calibration cup.

7. Turn the regulator’s on/off knob counterclockwise to open it. Gas will begin to flow.
8. Allow the gas to flow for 2 minutes.

9. Verify a voltmeter reading of 100 mV (±2 mV).

Содержание 65-2422RK-05

Страница 1: ...www rkiinstruments com 65 2422RK 05 Hydrogen Sulfide Transmitter Operator s Manual Part Number 71 0114RK Revision D Released 6 12 20...

Страница 2: ...calibration and maintenance of the detector is essential for proper operation and correct readings Please calibrate and maintain this detector regularly Frequency of calibration depends upon the type...

Страница 3: ...ent costs local repair costs transportation costs or contingent expenses incurred without our prior approval THIS WARRANTY IS EXPRESSLY IN LIEU OF ANY AND ALL OTHER WARRANTIES AND REPRESENTATIONS EXPR...

Страница 4: ...e H2S Transmitter to a Controller 11 Startup 13 Introducing Incoming Power 13 Setting the Zero Signal 13 Maintenance 14 Preventive Maintenance 14 Troubleshooting 14 Replacing Components of the H2S Tra...

Страница 5: ...proper and safe operation of the 65 2422RK 05 and to minimize the risk of personal injury Be sure to maintain and periodically calibrate the 65 2422RK 05 as described in this manual Table 1 Specifica...

Страница 6: ...re 1 H2S Transmitter Component Location Test Point FB T P 4 20 OXY 24V G W Interconnect Terminal Strip Securing Screw 2 3 4 NPT Conduit Hub SP AN RD ZERO T P OXY TOXIC Span Potentiometer Factory Set P...

Страница 7: ...or within the detector housing A pre amplifier located between the sockets and two interconnect wires conditions the sensor s signal before the signal reaches the controller Housing Cap Cap Gasket The...

Страница 8: ...lector determines for which transmitter the amplifier is intended For H2S transmitters a jumper block is installed over the TOXIC selector see Figure 1 Detector Terminal Strip The detector terminal st...

Страница 9: ...2S detector and amplifier are factory mounted to the junction box Use the junction box s two mounting holes to mount the H2S transmitter to a vertical surface at the monitoring site Use the cover on t...

Страница 10: ...al to 69 cubic inches and rated explosion proof for ClassI Groups B C and D may be used 2 Remove the junction box cover 3 Guide the two wires that extend from the top of the H2S detector through the b...

Страница 11: ...the explosion proof classification of the H2S detector junction box combination a conduit seal must be used within 18 inches of the junction box conduit hub used for wiring to the controller 7 Connec...

Страница 12: ...d connect the cable s drain wire to an available chassis earth ground at the controller RKI controllers typically have a ground stud that can be used to ground the cable s drain wire 24V 4 20 TOXIC SP...

Страница 13: ...r is in a fresh air environment environment known to be of normal oxygen content and free of toxic and combustible gases it is not necessary to apply zero air when verifying or setting the fresh air r...

Страница 14: ...ive Maintenance This section describes a preventive maintenance schedule to ensure the optimum performance of the H2S transmitter It includes daily and quarterly procedures Daily Verify a display read...

Страница 15: ...2 If the calibration response difficulties continue replace the H2S sensor as described later in this section 3 If the calibration response difficulties continue contact RKI Instruments Inc for furthe...

Страница 16: ...off the controller 2 Turn off or unplug incoming power at the power source end 3 Remove the junction box cover 4 Disconnect the detector leads from the detector terminal strip 5 Unscrew and remove th...

Страница 17: ...box cover 4 Disconnect the detector leads from the detector terminal strip Note the position of the color coded leads as you remove them 5 Unscrew the detector from the junction box 6 Guide the detec...

Страница 18: ...rolled then more frequent calibration than every 3 months may be necessary Calibration This section describes how to calibrate the H2S transmitter It includes procedures to prepare for calibration set...

Страница 19: ...reading of 100 mV 2mV 4 If necessary use the zero pot on the amplifier to adjust the reading to 100 mV 2mV 5 Unscrew the regulator from the zero air calibration cylinder Leave the sample tubing connec...

Страница 20: ...Rubber retaining boot 14 2101RK Spacer between sensor and rubber boot 18 0405RK 01 Junction box without cover pre drilled for amplifier 18 0406RK Junction box cover 57 1060RK Amplifier specify target...