UNPACKING 

Remove cover and sides of the crate. Check for visual damages. 
 
Note:  Do not work on the voltage transformer with heavy tools such as hammers or crow 
bars. 

2   

TRANSPORTATION OF THE UNPACKED VOLTAGE TRANSFORMER 

Note:  The  voltage  transformer  must  only  be  lifted  and  transported  by  means  of  textile 
hoisting slings. 

 
 
a)  Attach two hoisting slings below the top shed. 

 

 
b)  Hang hoisting sling to crane hook. 
c)  Lift voltage transformer out of crate. 