RITZ MESSWANDLER
Installation
manual
EKM Im-0033e rev.: 0
page 2 of 3
1
UNPACKING
Remove cover and sides of the crate. Check for visual damages.
Note: Do not work on the voltage transformer with heavy tools such as hammers or crow
bars.
2
TRANSPORTATION OF THE UNPACKED VOLTAGE TRANSFORMER
Note: The voltage transformer must only be lifted and transported by means of textile
hoisting slings.
a) Attach two hoisting slings below the top shed.
b) Hang hoisting sling to crane hook.
c) Lift voltage transformer out of crate.