Assembly instructions - FORCE 825K/825KI
Carry out the excavation in the ground with the measurements indicated
in the image alongside and prepare a suitable draining foundation.
DRAINAGE TEST
Water has to drain out within 30/35 minutes. In case the water will remain
longer into the hole, it is necessary to drain the water out through a pipe
connected to a pit with an electric pump.
See the alongside image.
1500x1500 MIN.
B
C
495
1300
1800
A
A
: CONCRETE
B
: NON-WOVEN FABRIC
C
: DRAINING GRAVEL
IMPORTANT: Carefully vibrate the concrete!
1500x1500 MIN.
B
C
A
CEMENTO
TESSUTO NON TESSUTO
GHIAIA DRENANTE
D
D
IMPACT DIRECTION
CABLE CONNECTOR BOX
VERY IMPORTANT:
CONNEXION PIPELAND D.50
1500
1500
400
NON-WOVEN FABRIC
Dig a hole down to 1800mm and introduce approx 30lt of water.
Insert the foundation case in the excavation.
Attention: The case must
rest on the bottom of the excavation and must be perfectly vertical -
.
Important: In order to make inserting the case easier, preparation for the
Insert the 50 mm diameter corrugated sheath in the case using the metal
guide.
The corrugated pipe must enter a maximum of 2/3 cm inside of the metal
protection, so that it does not interfere when the bollard is later inserted.
Fix the case with cement.
-
der the cramp-iron is completely covered by concrete. Using a spirit
.