20 |
P a g e
1.12
HEADERS INSTALLATION
1.
Lift and place one header with rafter ties into the U-channels on two adjacent post-top brackets. Rafter ties should be
on the header face that touches the vertical posts.
2.
Center the header between the two posts by measuring the overhangs and moving the header until the overhang
lengths on both sides are equal.
3.
Locate the two 5/16” holes, one on each wing extension of the post-top single header bracket. Drill 3/32” X 1-1/4”
deep pilot holes at the center of the two 5/16” Holes. Locate pilot holes at the center of each 5/16” hole.