INSTALLATION - EVACUATED TUBES
Rinnai 24
EVT DD Solar Pre Heat System Operation and Installation Manual
JOINING TWO COLLECTORS
Two EVT20A or EVT25A collectors
can be joined together for a 40 or 50
tube system, using kit DDEVTCPLKIT
Ensure insulation covers all exposed
fittings
PLUMBING CONNECTIONS AND TEMPERATURE SENSOR
The flow direction can be reversed from how it is shown in the diagrams below. Always ensure that the hot sensor
lead and the air bleed valve are positioned at the outlet end of the header.
Flow
Direc
tion
Flow
Direc
tion
Step 1.
Connect fittings to cold water side of header.
Copper flow pipework is supplied by installer.
Step 2. Connect hot sensor assembly to hot water
side of header Copper return pipework is
supplied by installer.
Flow
Direc
tion
Step 3. Connect temperature sensor lead into hot
sensor assembly. Ensure that the lead is
pushed all the way into the pocket.
Step 4. Secure the lead to the header using
silicone to ensure it will not come loose.
Connect the plug end to the solar controller
as described in the Operation / Installation
Manual - Rinnai Split Solar Hot Water
Systems.
Step 5.
Insulate all exposed fittings and pipework as described in the section ‘Water Pipes’ on page 9.