2.3
Moving and removing the packing
9
Wear suitable personal protection equipment when moving
the boiler and removing the packing. Only use lifting equip-
ment that is suitable for the weight involved.
− Remove the wooden cage (1)
− Remove the angular protections in polystyrene (2)
− Remove the protective bag (3).
1
4
5
3
2
2
1
Wooden crate
2
Edge protectors
3
Protective bag
4
Boiler
5
Pallet
9
The packaging material must be disposed of carefully and
must not be abandoned, as it is a source of potential dan-
ger.
Once you have removed the packaging, proceed as follows to
position the boiler:
− Pull the front panel towards you then lift it up to remove
it
HANDLING WITH SUPPORT RAILS
− Loosen the screws (6) fastening the pallet (5)
− Insert two pieces of tube (7) with suitable length in the
relevant holes, letting them come out evenly from both
sides. Use the protruding lengths of pipe as lifting han-
dles.
6
5
7
9
Take care because the boiler might swing when lifted.
Содержание TAU Unit 100
Страница 1: ...cod 20144127 rev 8 01 2021 TAU Unit 50 70 100 115 EN INSTALLATION AND MAINTENANCE MANUAL...
Страница 137: ...137 SYSTEM MANAGER...
Страница 138: ...138 SYSTEM MANAGER...
Страница 139: ...139 SYSTEM MANAGER...