Checklist for step-by-step installation procedure
The table below can be used as a checklist for the installation and commissioning
procedure for the FertiMiX Pro C. The right column shows page references to the
relevant sections.
You can use the spaces in the left column to tick off each step as you complete it.
This procedure assumes that:
Synopta and the Ridder CX500 have been installed.
the dealer is familiar with CX Assistant.
Completed No.
Step
Section to see for
this
Installation
1
Water installation
Connect the FertiMiX to the
water inlet and outlet pipes.
Connect the supply hoses for
fertilizers (and acid) to the
dosing channels.
"Connecting water
supply (hydronic
installation)" on
page 33.
2
Electrical installation
Connect the power supply,
network cable, external meters
and valves.
"Connecting electrical
components" on
page 33.
3
Where applicable: connect the extra
dosing channels, sensors, filling pump
and/or I/O modules.
"Installing other
components" on
page 34.
Commissioning
4
Use the latest version of the CX
Assistant, Ridder CX500 and Synopta
software.
"Updating software"
on page 37.
5
Software configuration
Create a configuration with CX
Assistant.
Check the configuration.
Upload the configuration to the
IPC.
"Software
configuration" on
page 38.
6
Check the settings (of the Ridder
CX500 controls) in Synopta.
"Software settings" on
page 44.
7
Calibrate the EC and pH sensors.
"Calibrating the
sensors" on page 45.
8
Pressurize the FertiMiX.
"Pressurizing the
FertiMiX" on page 45.
FertiMiX
60