![Reznor OH Скачать руководство пользователя страница 8](http://html1.mh-extra.com/html/reznor/oh/oh_installation-operation-and-maintenance-manual_1449861008.webp)
8
I-OH (01-20) PN120390R7
INSTALLATION—CONTINUED
Unpacking Unit
⚠ CAUTION ⚠
To prevent damage to the painted cabinet, it is recommended that the crate bottom be left in place
until after the unit has been suspended.
NOTE:
• A cleaning rake base is included with all units. If the heater is being installed in Canada, a
barometric draft regulator (option DB1, shipped separately) is required.
• The installation could also include a variety of other shipped-separate options. Ensure that all
optional components to be used in the installation are at the job site.
• The unit was inspected and tested at the factory prior to crating and was in operating condition
at that time.
Immediately upon uncrating the unit, check for any damage that may have occurred during shipping. If any damage is
found, immediately document the damage with the transporting agency and contact an authorized Reznor Distributor.
If you are an authorized Distributor, follow the FOB freight policy procedures as published by Reznor, LLC.
Unit Mounting
⚠ CAUTION ⚠
The unit must be level for proper operation.
The unit may be suspended or mounted on an optional workbench fuel tank (option OT) and heater stand (option
HS). Ensure that adequate clearances (refer to
) are available to accomodate the heater’s dimensions (refer
to
).
Suspension Mounting
Hang the heater as follows.
⚠ DANGER ⚠
• To prevent injury, death, or equipment damage, before suspending the heater, check the supporting
structure to ensure that it has sufficient load-carrying capacity to support the weight (refer to
• Before lifting the heater into place, ensure that the lifting device is rated to adequately supprt
the weight of the heater.
• Do not place on or add additional weight to the suspended heater.
NOTE: Units manufactured
before
OCT 1994 are suspended using 3/8-inch rods and hardware.
1. Attach suitable lifting device to heater and lift it into position.
2. To suspend heater using 1/2-inch threaded rod, lock four threaded rods using washers and nuts as shown in
pipe, lock four threaded pipes using swivel connectors, washers, and nuts as shown in
3. Remove shipping crate bottom from heater.
4. Remove shipping crate angle clips from heater and reinstall screws into heater cabinet.
5. Remove lifting device from heater.