R-8471/R-8472

Retractable Bollard Installation

Inspect the installation. 

Abrasions should be covered 

as soon as possible. For damage repair or other 

servicing needs, please refer to 

http://www.reliance-foundry.com/wp-content/

uploads/retractable-bollard-service-guide.pdf

STEP 6: 

Back fill the drilled hole with drain rock so that when 

the bollard assembly is placed in the site, the top edge of the 

receiver will sit at approximately 1/4" above grade. 

Install the Bollard Assembly

STEP 7: 

Keep the bollard assembly in its protective packaging. 

When ready to install, remove the protective packaging.

STEP 8: 

Place the bollard assembly in the center of the 

installation hole. Ensure that the top edge of the receiver sits 

at approximately 1/4" above grade. This will allow a slight 

berm to be created with concrete.

STEP 9: 

Extend or raise the bollard from the bollard assembly 

to its upright position. Hold a level against it and ensure that 

the bollard is plumb.

STEP 10: 

Back fill around the receiver up to approximately 

18" with the frost line in mind. Fill from the bottom tamp to 

ensure the bollard is stable and still plumb.

STEP 11: 

Turn the key to collapse the bollard back into the 

bollard assembly, ensuring not to disrupt the assembly’s 

position. 

Note: For the R-8471/R-8471-RA models, the key 

is used only used for collapsing the bollard into the bollard 

assembly. For the R-8472/R-8472-RA models, the key is used 

for both extending and collapsing the bollard from the bollard 

assembly.

Pour the Concrete

STEP 12: 

Mix the concrete. Check that the proper ratio of 

water and concrete mix is used—the concrete should have a 

similar texture to moldable clay.

 

STEP 13: 

Pour the concrete evenly into the site. The concrete 

should be slightly raised towards the top edge of the receiver 

to create a slight berm. Avoid disrupting the bollard assembly.

STEP 14: 

Allow the concrete to cure for a minimum of 

2–3 days. 

Note: Moisture in the environment and cool 

temperatures can significantly slow the process.

1/4"

18"

STEP 9

STEP 8

STEP 10

STEP 13