Decorative Bollard Cover Installation
Threaded Rod
in New Concrete
STEP 7 (A)
STEP 7 (C)
STEP 8 (B)
STEP 8 (C)
STEP 5:
Clean the surface of the pipe bollard. Debris can
offset measurements and the placement of the bollard
cover.
STEP 6:
Keep the bollard cover in its protective packaging
and place near the installation site. When ready to install,
remove its protective packaging.
Install the Bollard Cover
There are two options for installing the bollard cover and
inserting the threaded rod.
[OPTION 1: Insert the threaded rod after bollard cover
placement]
STEP 7 (A):
Lift the bollard cover and carefully lower over
the pipe bollard so that the pipe bollard is centered in the
bollard cover’s shaft.
Note: Metal bollard covers can be
heavy—ensure the proper resources are available to lift
them.
STEP 7 (B):
Fix the 1
"
nut to the bottom portion of the
threaded rod.
STEP 7 (C):
Push the threaded rod into the concrete down
the center of the pipe bollard. Leave an allowance at the
top for the washer and 1
"
nut.
[OPTION 2: Insert the threaded rod prior to bollard cover
placement]
STEP 8 (A):
Fix the 1
"
nut to the bottom portion of the
threaded rod
.
STEP 8 (B):
Push the threaded rod into the concrete down
the center of the pipe bollard. Leave an allowance at the
top for the washer and 1
"
nut. Check that the threaded rod
is centered and ensure it is plumb.
STEP 8 (C):
Lift the bollard cover and carefully lower it over
the pipe bollard and threaded rod. Ensure the pipe bollard
is centered in the bollard cover’s shaft and the bollard
cover is plumb.
Note: Metal bollard covers can be heavy—
ensure the proper resources are available to lift them.