Decorative Bollard Cover Installation

Threaded Rod 

in New Concrete

STEP 7 (A)

STEP 7 (C)

STEP 8 (B)

STEP 8 (C)

STEP 5:

 Clean the surface of the pipe bollard. Debris can 

offset measurements and the placement of the bollard 

cover.

STEP 6: 

Keep the bollard cover in its protective packaging 

and place near the installation site. When ready to install, 

remove its protective packaging.

Install the Bollard Cover

There are two options for installing the bollard cover and 

inserting the threaded rod.

[OPTION 1: Insert the threaded rod after bollard cover 

placement]

STEP 7 (A): 

Lift the bollard cover and carefully lower over 

the pipe bollard so that the pipe bollard is centered in the 

bollard cover’s shaft. 

Note: Metal bollard covers can be 

heavy—ensure the proper resources are available to lift 

them.

STEP 7 (B): 

Fix the 1

"

 nut to the bottom portion of the 

threaded rod.

STEP 7 (C):

 Push the threaded rod into the concrete down 

the center of the pipe bollard. Leave an allowance at the 

top for the washer and 1

"

 nut.

[OPTION 2: Insert the threaded rod prior to bollard cover 

placement]

STEP 8 (A):

 Fix the 1

"

 nut to the bottom portion of the 

threaded rod

.

STEP 8 (B): 

Push the threaded rod into the concrete down 

the center of the pipe bollard. Leave an allowance at the 

top for the washer and 1

"

 nut. Check that the threaded rod 

is centered and ensure it is plumb.

STEP 8 (C): 

Lift the bollard cover and carefully lower it over 

the pipe bollard and threaded rod. Ensure the pipe bollard 

is centered in the bollard cover’s shaft and the bollard 

cover is plumb. 

Note: Metal bollard covers can be heavy—

ensure the proper resources are available to lift them.