Decorative Bollard Cover Installation

Threaded Rod 

in New Concrete

1-877-789-3245  |  [email protected]  |  www.reliance-foundry.com

Bollards shown in the diagrams may not be the same model as the bollards shipped in this order. This does not affect the integrity of the installation.

To protect the finish, keep bollard covers in 

packaging until exact moment of installation.
Handle with care to avoid scratching or 

damaging bollard cover surfaces as abrasions 

will lead to rust. 

Parts List 

Installation Equipment

#

PART

QTY

1

Decorative Bollard Cover

1

2

Decorative Bollard Cap

1

3

Threaded Bar 1"

1

4

Washer 1"

1

5

Hex Nut 1"

2

6

Hexagon Socket Set Screw

3

7

Plastic Plug

3

3/16" Hex Key 

Shovel

1-1/2" Wrench 

Measuring Tape

Before Installation

STEP 1: 

Examine the pre-installed pipe bollard for signs 

of damage. Any rust should be removed, and abrasions 

should be covered. If the damage is beyond repair, a 

new pipe bollard may need to be installed. Ensure the 

pipe bollard does not have any pre-existing concrete fill.

STEP 2: 

Hold a level vertically against the side of the 

pipe bollard and ensure that it is plumb. 

Note: Any 

damage or tilting of the pipe bollard can affect the 

performance of the bollard cover.

Fill the Pipe Bollard

STEP 3: 

Mix the concrete. Ensure that the proper ratio 

of water and concrete mix is used.

STEP 4: 

Using a shovel, fill the pipe bollard with concrete 

leaving approximately 1

"

 of the top clear. Create a flat 

surface at the top

.

1