4.3
Inspection Types
Type
Description
Pre-use check
A check of key areas prior to each use without dismantling the
assembly. Carried out by a competent person.
Visual
A careful and critical assessment of the components, carried out by a
competent person without dismantling the assembly.
Examination
A careful and critical assessment of the components, carried out by a
competent person. This includes dismantling the assembly and
performing a visual assessment of the condition of each component
specified in the examination procedure, supplemented by other means
such as measurement and non-destructive testing as considered
necessary. For lifting assemblies this should include a visual inspection
of the condition of each leg.
Post Load Test
Inspection
A careful and critical assessment of the components following a proof
load test. Carried out by a competent person without dismantling the
assembly.
Table 13 WAVE Inspection Types
All inspections should be:
i.
Performed by a competent person.
ii.
Carried out as per the frequency indicated in the usage table.
iii.
Formally recorded.
General Guidance
i.
If there is any doubt regarding the usage of the equipment, then it is recommended
that the maintenance strategy should revert to a more conservative, higher usage
category.
ii.
This recommendation applies to change out of components parts only and does not
replace or alter the inspection intervals as prescribed by the relevant legislation.
iii.
Details of all damage should be recorded in a damage report. Details of the cause of
the damage should also be recorded, if known.
iv.
If damage to the frame has occurred, welds should be examined for cracks using dye
penetrant.
v.
Details of all repairs or modifications carried out should be recorded and copies of
damage and repair should be sent to the party controlling the use of the WAVE.
vi.
If the wire rope lifting assembly is removed and placed into storage, the covers
should be removed to prevent the build-up of condensation.
vii.
Contact RML or one of our approved partners for technical advice on inspection,
testing or maintenance. Send your query to