SECTION I: ELECTRICAL POWER CONNECTIONS

Installations must follow these codes:

·

National Electrical Code and any other national, state, provincial or local codes or regulations having
jurisdiction.

·

Safety wiring must be N.E.C. Class 1.

·

Boiler must be electrically grounded as required by N.E.C. ANSI/NFPA 70-latest edition.

·

In Canada, C.S.A. C22. 1 C.E.C. Part 1.

The boiler is wired for 120 Volts.

 The voltage is indicated on the tie-in leads. Consult the wiring diagram shipped with

the boiler in the instruction packet. The “TH” leads are connected to the remote tank control stat, thermostat, or elec-
tronic boiler control as applicable. 24 Volts are supplied to this connection through the boiler transformer. DO NOT
attach line voltage to the “TH” leads. Before starting the boiler check to insure proper voltage to the boiler and pump.

Install a separate disconnect means for each load. Use appropriate-sized wire as defined by NEC,  CSA and/or local code. All
primary wiring should be 125% of minimum rating.

It is strongly recommended that all individually-powered control modules and the boiler should be supplied from the same
power source.

SURGE PROTECTION

Microprocessor-based and solid state controls are vulnerable to damage from voltage and amperage fluctuations in the
power supply. All sensitive control components should be protected by a suitable commercial-grade surge protection
device.

If any of the original wire as supplied with the boiler must be replaced, it must be replaced with 105°C wire or its
equivalent.

CHECK THE POWER SOURCE

Using a volt-ohm meter (VOM), check the following voltages at the circuit breaker panel prior to connecting any equipment:
Make sure proper polarity is followed and house ground is proven.

FIGURE I-1

AC = 108 Volts AC Minimum, 132 Volts MAX

CHECK POWER SOURCE

AB = 108 Volts AC Minimum, 132 Volts MAX
BC = Must be less than 1.0 Volts AC

Fig # 9237

Содержание 500

Страница 1: ...dedwiththisboiler Installation and servicemustbeperformedbyaqualifiedinstaller service agencyorthe gassupplier FORYOURSAFETY WHAT TO DO IFYOU SMELLGAS Do not trytolightanyappliance Do not touchanyelec...

Страница 2: ...and vapors 2 Never cover the boiler lean anything against it store trash or debris near it stand on it or in any way block the flow of fresh air to the boiler WARNING More than one 1 supply source Th...

Страница 3: ...H GAS SUPPLY CONNECTIONS 24 SECTION I ELECTRICAL POWER CONNECTIONS 27 SECTION J VENTING CONNECTIONS 49 SECTION K CONDENSATE DRAIN 50 SECTION L CONTROLS 56 SECTION M GENERALSAFETYPRECAUTIONS 57 SECTION...

Страница 4: ...sentative Thank you for purchasing a Raypak product We hope you will be satisfied with the high quality and durability of our equipment PRODUCT RECEIPT On receipt of your product it is suggested that...

Страница 5: ...under the applicable American National Standard CSA Standard for USA and Canada Each boiler is constructed in accordance with Section IV of the American Society of Mechanical Engineers ASME Boiler Pre...

Страница 6: ...6 FigureA 1 ADVANCED DESIGN BOILER COMPONENT LOCATIONS...

Страница 7: ...pproved for and can be installed on a combustible surface but must NEVER be installed on carpeting Gas fueled equipment installed in enclosed parking garages must be located at least 18 inches above t...

Страница 8: ...OVE INSTALLATIONS Boiler Size Boiler Side 500 750 1000 Floor See Note 1 Rear 1 1 1 Right 12 Water side 12 Water side 12 Water side Left 1 1 1 Top 0 0 0 Vent 1 1 1 Note 1 Do not install on carpeting Fi...

Страница 9: ...ilers installed under overhangs TABLE 2 OUTDOOR INSTALLATION MINIMUM CLEARANCES Boiler Size Boiler Side 500 750 1000 Rear 6 6 6 Right 36 Water side 36 Water side 36 Water side Left 36 36 36 Top 0 0 0...

Страница 10: ...lding If all combustion air is drawn from the air inside the building the mechanical equipment room does not receive air from outside 1 The mechanical equipment room must be provided with two permanen...

Страница 11: ...ed fan assisted or power draft assisted burners there shall be a permanent air supply opening s having a cross section area of not less than 1 sq in per 7000 BTUH 310 sq mm per kW up to and including...

Страница 12: ...he boiler and the rest of the system prior to operation This is particularly true for hydronic systems using expensive glycol based antifreeze Raypak recommends conducting the hydrostatic test before...

Страница 13: ...Delta T as design Delta T Delta T is the temperature difference between the inlet and outlet water when the boiler is firing at full rate If a Delta T larger than 20 F is necessary the bypass must be...

Страница 14: ...illed medium from entering the boiler The boiler piping system of a hot water heating boiler connected to heating coils located in air handling units where they may be exposed to circulating refrigera...

Страница 15: ...Figure E 2b SINGLE BOILER PRIMARY SECONDARY PIPING WITH CHX 15 Figure E 3a DUAL BOILER PRIMARY SECONDARY PIPING...

Страница 16: ...16 Figure E 3b DUAL BOILER PRIMARY SECONDARY PIPING WITH CHX Figure E 4a SINGLE BOILER LOWTEMPERATUREAPPLICATION HEAT PUMP PRIMARY SECONDARY PIPING...

Страница 17: ...ted flow rates for soft medium and hard water Hardness is specified as grains per gallon TABLEF 1 DOMESTICWATERHEATINGBOILER FLOWRATEREQUIREMENTS Delta T Temperature rise in F GPM Gallons per minute S...

Страница 18: ...18 FigureF 1bb SINGLE BOILER DOMESTIC HOT WATER WITH ONE STORAGE TANKAND CHX 2 pump system Figure F 1c SINGLE BOILER DOMESTIC HOTWATER WITH ONE STORAGE TANK ONE PRE HEATTANKAND CHX...

Страница 19: ...ss valve is critical to proper operation of the heater The bypass valve should be adjusted to achieve an inlet water temperature in the range of 90 F to 100 F and an outlet water temperature between 1...

Страница 20: ...content and dissolved solids in the water become too high scale forms inside the heat exchanger tubes reducing heater efficiency and also damaging the heater If the pH drops below 7 2 the heater will...

Страница 21: ...Figure G 3a DOUBLE BOILER POOL APPLICATION 21...

Страница 22: ...st pressure in the gas supply line before reconnecting the boiler and its manual shut off valve to the gas supply line FAILURE TO FOLLOW THIS PROCEDURE MAY DAMAGE THE GAS VALVES Over pressurized gas v...

Страница 23: ...NGS See Tables O 2 and O 3 for Pressure Settings page 60 VENTING OF DIAPHRAGM GAS COMPONENTS Boilers have gas train components that have diaphragms in their construction that are supplied with a bleed...

Страница 24: ...a separate disconnect means for each load Use appropriate sized wire as defined by NEC CSAand or local code All primary wiring should be 125 of minimum rating It is strongly recommended that all indiv...

Страница 25: ...rovide an external surge suppressor capable of maintaining system integrity 5 Provide overload protection and a disconnect means for equipment serviceability as required by local and state code 6 Inst...

Страница 26: ...re for the remote tank control through the boiler transformer DO NOT attach line voltage to the TH leads Before starting boiler check to insure proper voltage to boiler and pump BREAK THE WIRE NUTAT T...

Страница 27: ...ent pressure and with a vent gas temperature that avoids excessive condensate production in the vent Category IV A boiler which operates with a positive vent pressure and with a vent gas temperature t...

Страница 28: ...ination for Venting Purpose and Venting Arrangement 28 NOTE PVC or CPVC vent maybe used inconjunction with CHX special piping arrangement has to be made Contact manufacturer for details A D B V E N T...

Страница 29: ...ocate or guard vent to prevent condensate from damaging exterior finishes Use a 2 x 2 rust resistant sheet metal backing plate against brick or masonry surfaces j DO NOT extend exposed vent pipe outsi...

Страница 30: ...he protective screen on the combustion air blower may be relocated to the air inlet termination elbow to act as an inlet screen WARNING Examine the venting system at least once a year Check all joints...

Страница 31: ...ALVENT WITHOUTADD ON CONDENSING HEAT EXCHANGER NOTE Rear venting is recommended to minimize interference with water piping Vent lengths are based on a lateral length of 2 feet Refer to the latest edit...

Страница 32: ...gn and weight of the material employed to maintain clearances and to prevent physical damage or separation of joints Natural Draft Vertical Vent Termination The vent terminal should be vertical and sh...

Страница 33: ...being inspected Follow the manufacturers instructions for lighting each appli ance Adjust thermostat so appliance will operate continuously e Test for natural draft negative pressure 12 above the out...

Страница 34: ...lation These installations utilize the boiler mounted blower to vent the combustion products to the outdoors Combustion air is taken from inside the room and the vent is installed horizontally through...

Страница 35: ...at a The vent be installed with a slight upward slope of not more than 1 4 per foot of horizontal run to the vent terminal In this case an approved condensate trap must be installed per applicable cod...

Страница 36: ...SECTION J 3 Horizontal Thru Wall Direct Venting Combustion Air Category III Figure J 3 HORIZONTAL THRU WALL DIRECT VENTING WITHOUT ADD ON SECONDARY CONDENSING HEAT EXCHANGER See notice next page 36...

Страница 37: ...t terminal In this case an approved condensate trap must be installed per applicable codes b The vent be insulated through the length of the horizontal run Horizontal Thru wall Direct Vent Termination...

Страница 38: ...4 VERTICAL DIRECT VENTING WITHOUT ADD ON CONDENSING HEAT EXCHANGER Vent lengths are based on a lateral length of 2 feet Refer to the latest edition of National Fuel Gas Code for further details ANSI...

Страница 39: ...provided for drainage of condensate The horizontal breaching of a vent must have an upward slope of not less than 1 4 inch per linear foot from the boiler to the vent terminal The horizontal portions...

Страница 40: ...ECTION J 5 Vertical Venting With Add On Condensing Heat Exchanger Category IV Domestic Water Figure J 5 VERTICALVENT CATEGORY IV WITHADD ON CONDENSING HEAT EXCHANGER Contact Manufacturer for Details 4...

Страница 41: ...alled to prevent the flue gas leakage Care must be taken during assembly to insure that all joints are sealed properly and are airtight For certain installations i e pool heat pump domestic hot water...

Страница 42: ...ION J 6 HorizontalThru wallVentingWithAdd onCondensingHeatExchanger CHX Figure J 6 HORIZONTAL THRU WALL VENTING WITH ADD ON CONDENSINGHEATEXCHANGER 42 Contact Manufacturer for Details See notice next...

Страница 43: ...nsure that all joints are sealed properly and are airtight For certain installations i e pool heat pump domestic hot water supply with pre heat tank PVC or CPVC may be used Contact manufacturer for de...

Страница 44: ...zontal Thru Wall Direct Venting Combustion Air With Add On Condensing Heat Exchanger Category IV Figure J 7 HORIZONTAL THRU WALL DIRECT VENTING WITH ADD ON CONDENSINGHEATEXCHANGER 44 Contact Manufactu...

Страница 45: ...mp domestic hot water supply with pre heat tank PVC or CPVC may be used Contact manufacturer for details To prevent condensate accumulation in the vent it is required to install the horizontal portion...

Страница 46: ...J 8 Vertical Direct Venting Combustion Air With Add on Condensing Heat Exchanger Category IV Figure J 8 VERTICALDIRECTVENTINGWITHADD ON SECONDARYCONDENSINGHEAT EXCHANGER 46 Contact manufacturer for d...

Страница 47: ...ic hot water supply with pre heat tank PVC or CPVC may be used Contact manufacturer for details To prevent the condensation accumulation in the vent it is required to install the horizontal portion of...

Страница 48: ...clearances must be observed to prevent restriction of combustion and ventilation air Keep area clear and free of combustible and flammable materials c Do not locate adjacent to any window door walkwa...

Страница 49: ...er to NFGC section 7 9 for additional information The Condensing Heat Exchanger CHX can generate up to 1 one gallon per hour GPH of condensate for every 100 000 BTUH The maximum condensation rates for...

Страница 50: ...CPW Central Point Wiring is an advanced control integration technique that provides complete boiler diagnostic capability and greatly simplifies troubleshooting At the heart of CPW is the Operations...

Страница 51: ...he boiler outlet increases more than 5 F after the pump turns off following a firing cycle the pump off time delay should be extended by thirty seconds Increase or decrease time delay as appropriate u...

Страница 52: ...ystem Enabled Yellow U 2 Diagnostics safety board is functional Manual High Limit Red Water temperature is over the manual high limit setting Auto High Limit Red Water temperature is over the auto hig...

Страница 53: ...53 Figure L 2 WIRINGDIAGRAM...

Страница 54: ...ly lit when the device is powered and pre purged Unit performs its own safety check and opens the main valve only after the pilot is proven to be lit HIGH LIMIT MANUAL RESET This appliance is equipped...

Страница 55: ...drops below the factory setting of 6 W C for Natural gas and 10 W C for propane gas The high gas pressure switch optional mounts down stream of the gas pressure regulator If the gas pressure regulato...

Страница 56: ...may be used as a guide in determining the safest water temperature for your applications Temperature Time to Produce Serious Burn Temperature Time to Produce Serious Burn 120 F More than 5 minutes 140...

Страница 57: ...ING smell all around the appliance area for gas Be sure to smell next to the floor because some gas is heavier than air and will settle on the floor 3 WHATTO DO IFYOU SMELLGAS Do not try to light any...

Страница 58: ...58 Figure O 1 COMPONENTAND PRESSURE TAPLOCATIONS Blower T fitting detail...

Страница 59: ...may burn out 120V 24V transformer or may cause other safety control damage or failure 2 2 Attach Manometers to Measure Pressures See Figure O 1 Attach 16 scale manometer to the first main gas shut off...

Страница 60: ...observe through view port for spark 4 If you do not see spark turn off power check ignition wire and proper grounding and wiring Turn power back on Repeat Step 1 If there is still no spark after sever...

Страница 61: ...ially manifold pressure within 0 1 of listed values Your ADB is tuned in 3 4 Safety Inspection Check all thermostats and high limit settings Attach thermometers to IN OUT piping and take the temperatu...

Страница 62: ...should fail to light The standard lockout time is 90 seconds then the pilot light goes off and the boiler goes into post purge If the lockout module is attached to boiler a lockout light comes on Turn...

Страница 63: ...sired setting The appliance will operate The pilot burner will light after the pre purge time delay 45 seconds Then the pilot will light the main burner 10 If the appliance will not operate follow the...

Страница 64: ...ntial of severe burn DO NOTREST HANDS ON OR GRASPPIPES Use a light touch return piping will heat up quickly 12 If mixing valve does not seem to be working the spring and thermostat may need to be repl...

Страница 65: ...t these procedures 1 If you find soot in top of vent elbow some sediment in bottom of vent is normal remove vent attachment to theADB and clean flue exhaust baffle inside the boiler Also check burner...

Страница 66: ...10 Connect the flue vent Category IV venting UL 17 38 Certified Venting Material to the 15 elbow of the CHX flue outlet 11 Connect the PVC pipe not supplied for condensate water disposal check with l...

Страница 67: ...metallic vent pipe In extremely contaminated area this may also experience deterioration Products causing contaminated combustion air spray cans containing chloro fluorocarbons permanent wave solution...

Страница 68: ...68...

Страница 69: ...69...

Страница 70: ...70...

Страница 71: ...71...

Страница 72: ...72...

Страница 73: ...ff ______ W C Pilot ______ W C Main Burner ______ W C Blower burner on ______ W C Supply Gas static ______ W C Supply Gas dynamic ______ W C Power Supply ______ Volts EMISSION Analyzer readings CO2 __...

Страница 74: ...AX 800 872 9725 Raypak Canada LTD 2805 Slough Street Mississauga Ontario Canada L4T1G2 905 677 7999 FAX 905 677 8036 RaypakAustralia Pty Ltd 7 Geddes Street Mulgrave Victoria Australia 3170 613 9560 4...