During the production of steam, the concentration of minerals inside the steam generator will
increase over time. These minerals settle on the heating elements and heat exchanger as
well as the interior steam generator walls.
In order to reduce this effect the steam generator will be pumped off and flushed regularly depending
on the duration of steam production. This process needs approximately 45 seconds.
After emptying the steam generator it will be filled automatically with fresh water.
There are 4 conditions to start this SC Automatic:
1. Heating time of the steam generator must exceed 60 min.*
and
2. the temperature of the thermocouple steam generator must be below 65°C (149°F)
and
3. the temperature of the thermocouple interior cabinet must be below 70°C (158°F)
and
4. the unit is switched ON.
In case the unit is used permanently the above mentioned temperature conditions
can not be met.
In this case the following 2 conditions apply:
1. The heating time of the steam generator reaches the twice the set duration*, i.e. 120 min. and
2. the unit door is open for longer than 30 seconds
* The marked values can be changed in unit specific ranges using the diagnostic program
(see modules SCC and CM).
SCC Index G: 120 min.
After completion of the SC-Automatic the accumulated steam heating time is re-set to zero.
SC-Automatic does not replace the need for descaling and/or installing water treatment filter
SC (Self Clean) Automatic
Содержание SelfCooking Center Combi Master
Страница 1: ...Training manual Fundamentals SCC Line SelfCooking Center Combi Master...
Страница 7: ...7 V03 EN Fundamentals Control panel Layout SCC Line CPC Line C Line Classic Line CM SCC...
Страница 31: ...31 V03 EN Fundamentals...
Страница 38: ...V03 EN Fundamentals 38...
Страница 39: ...39 V03 EN Fundamentals...