7.1 Changing Vent and Air Intake Orientation
The heater is sold with rear horizontal vent and air
intake connections as standard. (only separated
combustion models have air intake connection). If
vertical vent and air intake connections are required,
follow the instructions
7.2 Venting
This heater must be vented in accordance with the
rules contained in this manual and with the following
national codes and any state, provincial or local
codes which may apply:
United States:
Refer to
NFPA 54/ANSI Z223.1 - latest revision, National
Fuel Gas Code;
Canada:
Refer to CSA B149.1
Natural Gas and Propane Installation Code.
Any portion of vent pipe passing through a
combustible wall must have a listed thimble to
conform with the above codes.
The bottom of the vent or air intake terminal shall not
be located less than 1' (.3 m) above grade level.
The vent shall not terminate less than 7' (2.1 m)
above grade where located adjacent to public
walkways.
Vent terminal must be installed at a height sufficient
to prevent blockage by snow and building materials
protected from degradation by flue gasses.
Vent terminal must be beyond any combustible
overhang.
Secure all joints with corrosion resistant #8 x 3/8"
sheet metal screws.
For single wall venting, pressure sensitive aluminum
tape or silicone sealant must be used to seal all
joints.
Aluminum tape shall have a minimum temperature
rating of 400° F (204° C) and meet SMACNA AFTS-
100-73 standards. High temperature silicone sealant
must have a minimum temperature rating of 480° F
(250° C).
7.2.1 United States Requirements
Vent must terminate at least 3' (.9 m) above any
forced air inlet located within 10' (3.1 m).
Vent must terminate at least 4' (1.2 m) below,
4' (1.2 m) horizontally from, or 1' (.3 m) above any
door, operable window, or gravity air inlet into any
building.
NFPA 54/ANSI Z223.1 - latest revision, National
Fuel Gas Code specifies a 4' (1.2 m) horizontal vent
terminal clearance from gas and electric meters,
regulators and relief equipment.
7.2.2 Canadian Requirements
The vent shall not terminate within 6' (1.8 m) of a
mechanical air supply inlet to any building.
The vent shall not terminate within 3' (.9 m) of a
window or door that can be opened in any building,
any non-mechanical air supply inlet to any building,
or of the combustion air inlet of any other piece of
equipment.
7.3 Vent Installation
Maintain clearances to combustibles at all times for
safety. Clearances are the required distances that
combustible objects must be away from the heater
to prevent serious fire hazard.
For vented units, the vent must terminate outside of
the building.
Vents must be fully sealed and correctly sized for
the model. If the vent passes through a wall or
ceiling of combustible material, it must be enclosed
by a listed thimble and be separated from the
thimble by at least a 2" (5 cm) air gap.
For separated combustion models, vents and air
intakes must be a fully sealed system and correctly
sized for the model. Vent should be assembled as
detailed
. The joints between the vent terminal and
the roof or wall must be properly sealed.
Vents and air intakes must be adequately
supported so that the heater does not bear the
weight of the pipes.
For vent termination
WARNING
Carbon Monoxide Hazard
Heaters must be vented
outdoors.
Heaters must be installed
according to the
installation manual.
Failure to follow these
instructions can result in
death or injury.
Содержание UHDS 100
Страница 2: ......
Страница 4: ......
Страница 6: ......
Страница 8: ......
Страница 28: ...UHD LOW PROFILE DUCT FURNACE INSTALLATION OPERATION AND SERVICE MANUAL 20 of 45 Figure 14 Gas Connection ...
Страница 42: ...UHD LOW PROFILE DUCT FURNACE INSTALLATION OPERATION AND SERVICE MANUAL 34 of 45 14 1 General ...
Страница 54: ......
Страница 55: ......
Страница 56: ......
Страница 57: ......
Страница 58: ......