2. Press the power switch on the front of the instrument. The instrument starts the
booting process and all modules are supplied with power.
2.3.3.3
Start Screen and Booting of the R&S UPV
After the instrument is turned on, the BIOS version that is installed and the computer
characteristics are displayed on the screen for several seconds.
Afterwards, the Windows operating system boots first followed by the instrument firm-
ware. A self-test is carried out while instrument firmware is booted. The most recent
instrument settings saved automatically at power-off are then loaded so that the instru-
ment is in the same state as it was before power-off. After booting is completed, the
audio analyzer screen is displayed and the instrument can be operated manually or via
remote control.
2.3.3.4
Restarting the R&S UPV
If the R&S UPV firmware was closed without shutting down the operating system (e.g.
by clicking on the
icon in the title bar or ALT F4 on the keyboard), the program can
be restarted with the mouse in two ways:
●
Clicking on the "R&S
UPV" icon on the desktop
●
Clicking on the Start button in the taskbar, and then selecting the folders "All Pro-
grams, Rohde & Schwarz, UPV" and clicking on the "R&S UPV" icon
If the software should crash unexpectedly and the instrument is operated via the front
panel, it can only be rebooted by pressing the power switch. When using an external
keyboard and a mouse, we recommend carrying out a warm start first using the short-
cut Ctrl+Alt+Del (restart) or trying the Restart icon with the green arrow.