4-8
Figure 4-6
Note:
The weld (1) of the vertical chain links shall be
towards
the chain sprocket
2-fall chain
1.
Insert the last chain link in the small plastic hook of the insertion tool.
2.
Insert the other side of the tool up through the sprocket, entering the chain container
side.
3.
Run the hoist at slow speed so that the tool and the chain come out the other side of the
sprocket. Continue until about 20” (50 cm) of chain becomes available.
4.
Put the chain through the idler sprocket,
making sure not to twist the chain during
installation.
5.
Remove the limit switch by removing the two screws.
6.
Remove the chain anchor from the hoist body.
7.
Disassemble the chain pin from the anchor.
8.
Insert the chain end to anchor and place the chain pin into its place to fix the chain.
9.
Reattach the chain anchor to the hoist body. Properly tighten bolts according to Torque
Specification, SECTION 5.
10.
Reinstall the limit switch to the chain guide. Properly tighten screws according to
Torque Specification, SECTION 5.
Run the load chain up and down a few times without load and make sure the load chain is not
twisted. Lubricate the load chain.