A
272
272
272
H4
H55
278
279
H3
H11
H17
H28
MONKEY BAR
MOUNTING
HOLES MUST BE
BY ROCK WALL
H55
H4
279
272
H3
H11
H17
H28
DETAIL A
1/2"
B
INSET A
COUNTER-SUNK
HOLES DOWN
279
*NOTE: Do not fully tighten hardware at this time.
*NOTE: 3/8" Hardware (H28) is shown in this step, but will not be installed until Step 8.
*NOTE: The counter-sunk holes in Top Joists (278) and (279) must face down (as shown in
INSET A).
1. Attach Top Joist with Monkey Bar Holes
(278)
and Top Joist with Swing Beam Holes
(279)
to
Corner Posts
(272)
using 3/8" Hardware
(H3) (H11) (H17) (H55)
and 1/2" Hardware
(H4)
. Top
Joist with Monkey Bar Holes
(278)
must be positioned so the Monkey Bar holes are on the side of
the set by the Rock Wall.
25
Step 7
Top Joists Installation