Before covering any  plumbing with hardscape or concrete, cap all spray 

lines and pressure test the system.  It is recommended the system be  

pressurized between 20psi and 25psi for a minimum of 2 hours.  Maintain 

a pressurized system during the concrete phase of construction to be sure 

no damage is done to the pipes.   

Your Splash Pad Product and Installation Resource 

Pressure Testing

 

Содержание Basic Splash Pad

Страница 1: ...Phone 888 445 RAIN Fax 866 869 3942 Email info RainDeck com Basic Splash Pad Installation Manual Rev 11 15 11 V 7...

Страница 2: ...pad to your needs All of our Splash Pad kits are com pletely expandable If during the course of installation you may require technical support or have questions regarding the Rain Deck product please...

Страница 3: ...er Surface Material Start Up Note To ensure the proper installation of the splash pad kit RainDeck highly recommends that you use qualified licensed tradesman for plumbing concrete or other trades as...

Страница 4: ...tallation of your splash pad Some municipalities may require a design with specific details Rain Deck has an experienced design team that can assist with the design and layout of your splash pad Pleas...

Страница 5: ...from manifold to splash pad Schedule 40 3 4 or 1 2 PVC fittings T s elbows couplings 45 s etc 4 drain pipe and fittings for drain line s 1 schedule 40 PVC pipe approximately 40 to 80 depending on dis...

Страница 6: ...Burial Grade Holding Tank 8 2 1 1 1 2 Bulk Head Fittings 9 Auto Water Leveler for Tank 10 1 Check Valve 11 1 5 HP Pool Grade Pump 12 150 Square Foot Pool Grade Cartridge Filter 13 Float Chlorinator Di...

Страница 7: ...s Do not permit any electrical apparatuses ie Radio TV etc within 10 feet 3m of splash pad surface EXTREME CAUTION Children should ALWAYS be supervised by a responsible adult while using the Rain Deck...

Страница 8: ...location plumbing runs electrical runs and equipment location before construction begins Excavate the splash pad area so that your finished concrete slab is at desired elevation Keep in mind that the...

Страница 9: ...concrete However if a surface material will be applied over the con crete ie Rubber lace we recommend using a 4 sleeve at the nozzle locations and setting the Rain Deck housings as a separate step af...

Страница 10: ...test the system It is recommended the system be pressurized between 20psi and 25psi for a minimum of 2 hours Maintain a pressurized system during the concrete phase of construction to be sure no damag...

Страница 11: ...einforcement requirements Depending on your area your project may have additional concrete requirements Please check with a professional to be sure you meet the minimum stan dards for a quality concre...

Страница 12: ...sing will be flush with the top of the finished surface material ie If rubber surfacing will be applied as a surface material set the housings above the finished concrete After the Rain Deck housing h...

Страница 13: ...specific instructions that came with your above ground water feature If you do not have the install detail sheet for the above ground water feature please contact Rain Deck before attempting installa...

Страница 14: ...up the system Once the system is running gradually open the 3 way valve to the splash pad side until desired pressure is achieved Rain Deck recommends using a qualified licensed plumber during this st...

Страница 15: ...ank be located on the outside perimeter of the concrete so it will be accessible for servicing On a standard splash pad with less than 20 spray jets use a 4 drain pipe See the dia gram below Your Spla...

Страница 16: ...the following page Please also refer to the installation instructions that came with the electronic controller This stage of installation requires an experienced licensed electri cian Please do not at...

Страница 17: ...ox This nut may need to be loosened to pass the wires through Step 4 Remove the green connector Step 5 Strip approximately inch of jacket from each solenoid wire Step 6 Begin installing hot leads on s...

Страница 18: ...op of the surface material When installing the surface material take precautions to ensure no debris enters the Rain Deck housings Generally taping off the opening on the Rain Deck housing will be suf...

Страница 19: ...p and filter In general you will need to fill the pump basket with water secure the pump lid and run the pump while bleeding air from the filter until completely primed Once the system is primed and r...

Страница 20: ...__________________________________________ ____________________________________________ ____________________________________________ ____________________________________________ ______________________...

Отзывы: