14
2. BOILER ASSEMBLY
The boiler must be installed on a concrete base about 100 mm in height from the
floor of the room. The boiler must be positioned so that the boiler is easily accessed
from all sides for cleaning and maintenance.
For normal operation of the boiler it is necessary to bring fresh air into the boiler
room. Air slot size of the boiler room must be of minimum dimensions of 200 mm x
200 mm.
For normal operation of the boiler it is necessary for the chimney to be of the
prescribed characteristics and made of coils of the secluded prescribed diameter
pipes.
Outlet into the chimney must go up the chimney, and any bend should not be with
sharp corners. Otherwise there is incomplete combustion and smoke is going
backwards into the boiler room.
The boiler and the installation must be equipped with adequate safety devices.
NOTE:
FOR THIS CONSTRUCTION OF BOILER THE INSTALLATION OF MIXING VALVE
IS REQUIRED OPERATING AND THE LOWEST TEMPERATURE OF 70 ° C., THIS
RESULTS IN THE HIGHEST POSSIBLE LEVEL OF UTILIZATION IN THIS DESIGN,
THE BEST COMBUSTION ELIMINATING THE BAD EFFECT OF CONDENSATION,
SO, THE OPERATING LIFE OF BOILER IS INCREASED.