ActiveScale™ P100E3 Support Guide
18
Figure 3
-
7. PSU failure (left) and online PSU (right) icons
3.1.4 Replacing P100E3 Nodes
Caution:
The P100E3 Node weighs 87 lbs (39.46 kg). Two people are required
to move it.
Table 3
-
8. P100E3 Node replacement overview
3.1.4.1 Removing a P100E3 Node
To remove a P100E3 Node:
1. Shut down the node. If the node is already powered down (for example, because it has failed), skip
this step.
Important:
Do not shut down a node unless all other nodes are healthy.
Figure 3
-
8. Resources > Rack > Node > Shutdown
a. Click
Resources.
b. On multi-site systems, select a site from the
Sites
pull-down menu.
c. In the
Racks
pull-down menu, select a system.
d. In the rack graphic, select the node you want to shut down. Typically, the node you want to shut
down has a failure icon overlay.
e. In the node’s
Actions
pull-down menu, select
Shutdown Node
.
Required tools
Personnel required
Replacement time
None
2