Pre-Installation Checklist
Before beginning the actual installation, the Site Implementation Engineer must perform the following tasks:
Step 1. Check the packing list to verify all ordered equipment has been
received. The box should contain:
❑
A SilverStorm 9120 switch with the following pre-installed:
❑
Four (4) fan units
❑
Power supplies and blanks (6 total).
❑
InfiniBand (IB) leaf modules (up to 12 total)
❑
Spine modules and blanks (up to 3 total)
❑
Virtual I/O hardware such as the SilverStorm™ FibreChannel Virtual I/O Card (FVIC) and the SilverStorm™
Ethernet Virtual I/O Card (EVIC) (up to 4 total)
❑
Any leaf/VIO hardware blanks (up to 11 total).
NOTE:
If using VIO hardware, in order to maintain AC redundancy, use the following configurations:
❑
1 VIO card and 11 leaf modules.
❑
2 VIO cards and 10 leaf modules.
❑
3 VIO cards and a
maximum
of 7 leaf modules.
❑
4 VIO cards and a
maximum
of 4 leaf modules.
NOTE:
Once the AC Redundancy threshold has been exceeded, the SilverStorm 9120 must use a
minimum of 4 power supplies and two power cords that must be plugged into a common, switched power
source (e.g., a power strip).
❑
Additional parts:
❑
One (1) Hardware installation kit (mounting rails, etc.)
❑
One (1) Serial cable DB-9 female to RJ-11 connectors
❑
One (1) Category RJ-11 Serial cable
❑
Power cords (up to 2 total)
NOTE:
Be certain that the power cords are firmly seated into the SilverStorm 9120 power supplies AC
power inlets.
❑