ePAQ-9405
User’s Guide
UG-1084
32
Test Panel
Copyright © 2017 QEI
NOTE
The display will indicate in decimal format and display the actual count, as
sampled (15-bit values).
When additional accumulator points are to be examined, press the
ENTER
key, the
accumulator points previously entered will scroll upwards to the next line on the
display and all values will be frozen. Then repeat step 1. by entering
RC
and the
desired accumulator point numbers. This procedure can be continued to examine
every accumulator point in the subsystem, if desired.
NOTE
Over a Remote based test panel connection, this command will continue to
update the screen after the 5 minute inactivity timeout has elapsed. When
you attempt to exit from this command (by pressing Enter), you will be
prompted to re-enter a valid username and password combination.
15.11 Relay Control
CAUTION
THE FOLLOWING PROCEDURE WILL ENERGIZE RELAYS CONNECTED
TO CONTROL POINTS. MAKE CERTAIN THAT EITHER IT IS SAFE TO
COMMAND THE POINT OR THAT THE FIELD DEVICE IS
DISCONNECTED FROM THE RELAY.
NOTE
When connected to the test panel via a Remote connection, Relay Control
commands are not available for security reasons.
Two (2) relay commands can be entered by the Test Panel to operate control relays.
Command CN will control a function 1 (ON) relay and CF will command a function 2
(OFF) relay.
15.11.1 On Relay Operation (CN)
To operate the function 2 (ON) relay on a control point (odd numbered
relays K1-K15 typically), type
CN
(space) and the point number of the
relay. Point numbers start with 0 (zero).
6. Press the
ENTER
key. The relay will operate.* All function 2 (ON)
relays may be controlled one at a time by repeating steps 1. and 2.,
and using different point numbers.
Содержание DIO-9110
Страница 1: ...UG 1084 ePAQ 9405 User s Guide December 2018 ...
Страница 4: ......