2
•
Close hole with earth.
Q-VAULT-5
STANDARD INSTALLATION
Continued
•
Install cover with Hex
screw by following the
number sequence.
NOTE
:
Maximum torque 50"lbs
1
2
4
5
6
3
Soil
Gravel
Drain Pipe
Soil
Gravel
Drain Pipe
•
Install Gasket.
Housing top before placing gasket
Gasket
Soil
Gravel
Drain Pipe
1.
•
Place drain pipe at the lowest
slope of land for proper
drainage. Fill bottom of pit with
4" of gravel.
16"
•
Place housing into Hole then
bring all primary and secondary
wiring into housing.
NOTE:
Using the Field Drill Guide
Labels provided in the installation
kit you are able to drill for various
fitting sizes.
2.
Soil
Gravel
Soil
30"
•
Prepare Excavated Hole:
30" x 16".
Drain Pipe
4"
3.
4.
•
Make Q-SET connection.
٭
Q-SET1: Fits 2
٭
Q-SET2: Fit 1
٭
Q-SET3: Fit 1
5.
6.
7.
Soil
Gravel
Drain Pipe
Gasket
Gasket
Drain Pipe
Land
NOTE
:
Q-SET Installation Instruction
on separate sheet in shipping box.