background image

4

5

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO ML-G9.X – Q CELLS

INSTALLATION AND OPERATION MANUAL SOLAR MODULES Q.PEAK DUO ML-G9.X – Q CELLS

Validity

These instructions are only valid for crystalline solar modules from 
the company Q CELLS as specified at chapter „2.1 Technical 
Specifications“. 
Q CELLS assumes no liability for damage resulting 
from failure to observe these instructions. 

 

Ä

Please observe the wiring and dimensioning of the system.

 

Ä

The installer of the system is responsible for compliance with all 
necessary safety regulations during set-up and installation.

Q CELLS assumes no liability on the basis of these instructions. 
Q CELLS is only liable in the context of contractual agreements 
or in the context of accepted guarantees. Q CELLS accepts no 
other responsibility for the functionality and safety of the modules. 

 

Ä

Please observe the instructions for any other system compo-
nents that may be part of the complete solar power system. 
It may be necessary to carry out a structural analysis for the 
entire project. 

Additional information for the Operator

 

Ä

Please keep this manual for the entire life of the solar power 
system.

 

Ä

Please contact your system supplier for information concerning 
the formal requirements for solar power systems.

 

Ä

Please be sure to contact the relevant local authorities and 
energy providers regarding regulations and permit requirements 
prior to installation of the solar power system. Your financial 
success depends on the fulfillment of these requirements.

Other applicable documents

In addition to this Manual following technical information are 
relevant:

DOCUMENT TYPE

Product data sheet

Packaging and transport information

Fig. 1: 

External dimensions and components for  
Q.PEAK DUO ML-G9, Q.PEAK DUO ML-G9+,  
Q.PEAK DUO BLK ML-G9 and Q.PEAK DUO BLK ML-G9+

DETAIL A

16 mm

8.5 mm

24.5 mm

1088 mm

1840 mm

4 × Mounting slots (DETAIL A)

Frame

1030 mm

981 mm

32 mm

8 × Drainage holes

376 mm

EN

4 × Grounding points ø 4.5 mm

Label

1200 mm

1200 mm

For additional information see the relevant datasheet of the module provided at www.q-cells.com.

PRODUCT LINE

Q.PEAK DUO ML-G9
Q.PEAK DUO ML-G9+

Q.PEAK DUO BLK ML-G9 
Q.PEAK DUO BLK ML-G9+

Type

Q.ANTUM DUO Z

Q.ANTUM DUO Z

Length

1840 mm

1840 mm

Width

1030 mm

1030 mm

Frame height

32 mm

32 mm

Area

1.90 m²

1.90 m²

Weight

19.5 kg

19.5 kg

Max. system voltage V

SYS

1000 V

1000 V

Max. reverse current

20 A

20 A

Permissible  

temperature range

–40 °C to +85 °C (–40 °F to +185 °F)

Junction box  

protection class

IP67 with bypass diode

Connector protection class

IP68

Fire rating based on 

ANSI / UL 61730

C / Type  2

C / Type  2

Max. test load Push/Pull

1

6,000 Pa / 4,000 Pa

6,000 Pa / 4,000 Pa

Max. design load Push/Pull

1

4,000 Pa / 2,660 Pa

4,000 Pa / 2,660 Pa

Certificates

CE-compliant; IEC 61215:2016; IEC 61730:2016; PV module classification: Class II;  
UL 61730

1

  Test and design load in accordance with IEC 61215:2016, depending on mounting options (see section „2.3 Mounting Options“)

1  INTRODUCTION

2  PLANNING

2.1  TECHNICAL SPECIFICATIONS

Содержание Q.PEAK DUO ML-G9 Series

Страница 1: ...INSTALLATION AND OPERATION MANUAL Q PEAK DUO ML G9 X solar module series Valid for Africa Europe LatinAmerica South America...

Страница 2: ...uch as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable laws and r...

Страница 3: ...rior to installation of the solar power system Your financial success depends on the fulfillment of these requirements Other applicable documents In addition to this Manual following technical informa...

Страница 4: ...rrosion Allows for stress free expansion and contraction due to temperature fluctuations Ensure that no additional forces are applied through the mounting system into the module except for the wind an...

Страница 5: ...termined with the following clamp parameters clamp width 40mm and clamp depth 10mm The system installer is responsible for the determination of location specific load requirements CL1a at high loads 5...

Страница 6: ...rence of reverse currents caused by module defects ground leaks or defective insulation Ensure that the maximum reverse current load capacity indicated in the data sheet is met In order to limit rever...

Страница 7: ...Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects to fall onto modules 3 INSTALLATION 3 1 SAFETY AND TRANSPORT Danger Risk of...

Страница 8: ...result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that the entire open c...

Страница 9: ...ed personnel see page 3 Ensure correct polarity Use solar cables for the connection at the junction box outlet Only interconnect connectors of the same type and manufacturer Use minimum 4mm2 copper wi...

Страница 10: ...he cabling is not exposed and or hanging and is protected from dirt moisture and mechanical friction 4 ELECTRICAL CONNECTION 4 4 AFTER INSTALLATION No dry cleaning or use of rotating brushes Modules m...

Страница 11: ...Do not carry or wear any electrically conductive parts WARNING Risk of falling due to unsecured access Never access the installation area alone or without taking adequate security precautions Please c...

Страница 12: ...e 17 21 06766 Bitterfeld Wolfen Germany TEL 49 0 34946699 23222 FAX 49 0 34946699 23000 EMAIL sales q cells com WEB www q cells com Subject to change without notice Q CELLS Installation manual solar m...

Отзывы: