Use solar cables for the connection at the 
junction box outlet. 

 

Ä

Use the same, inverter-compatible plugs.

 

Ä

Use minimum 4 mm

2

 copper wires insulated for 

a minimum of 90 °C for field connections.

NOTE! Module damage may occur!

 

Ä

Ensure that the cabling is not under mechanical 
stress (Comply with bending radius of ≥ 60 mm).

 

Ä

Ensure that the cables do not run between module 
and mounting rail or structure (danger of pinch).

 

Ä

Do not connect modules with different orien-
tations or angles of inclination in the same 
string.

 

Ä

Ensure for a tight connection between the 
plugs. Plugs click together audibly.

EN

click

DANGER! Risk of fatal injury due to electric 
shock! 

 

Ä

Ensure that all electrical components are in a 
proper, dry, and safe condition.

 

Ä

To avoid complex cabling arrangements, it is 
often advantageous to rotate some modules 
180°.

 

Ä

Module orientation can clearly be identified 
from the front side by the serial number and 
barcode labelled behind the module glass on 
the side with negative connection cable.

EN

Inverter

180°

180°

SOLAR

 

Ä

Ensure that all necessary safety and functional 
tests have been carried out according to 
applicable standards.

NOTE! Module damage may occur!

 

Ä

Ensure that the plug connections are secured 
away from any water-channelling surface.  

 

Ä

Integrate the system into the existing lightening 
protection system in accordance with the 
applicable local regulations.

WARNING! Fire Risk!

 

Ä

Do not use light concentrators (e.g. mirrors or 
lenses).

 

Ä

Ensure that the cabling is not exposed and/or 
hanging and is protected from dirt, moisture 
and mechanical friction.

 

Ä

Ensure that cables are protected from abrasion, 
tension, compression and cutting forces in full 
accordance with AS / NZS 3000 and all other 
relevant standards.

4  ELECTRICAL CONNECTION

4.3 CONNECTION OF MODULES

4  ELECTRICAL CONNECTION

4.4 AFTER INSTALLATION

 

Ä

No dry cleaning or use of rotating brushes. 

 

Ä

Modules must be cleaned manually and only 
with sufficient Water.

Содержание Q MAXX-G2 Series

Страница 1: ...INSTALLATION AND OPERATION MANUAL Q MAXX G2 solar module series Valid for Africa Europe LatinAmerica South America...

Страница 2: ...tions such as country specific regulations for pressure equipment operational safety hazardous goods and environmental protection Regulations and requirements specific to the system Any applicable law...

Страница 3: ...solar power systems Please be sure to contact the relevant local authorities and energyprovidersregardingregulationsandpermitrequirements prior to installation of the solar power system Other applica...

Страница 4: ...und the roof or the fa ade Forces acting on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Avoid the usage of different metals to prevent contact...

Страница 5: ...eet referring to the relevant Module available at www q cells com For maximum energy yields mismatches of specified elec tric current IMPP of more than 5 should be avoided for all modules connected in...

Страница 6: ...o not install damaged modules Inform your distributor of any damages immediately NOTE Module damage may occur Do not stack modules NOTE Module damage may occur Do not install modules near flammable ga...

Страница 7: ...ot modify the module e g do not drill any additional holes 3 INSTALLATION 3 2 PREPARATION OF INSTALLATION Option 1 Fasten the module with 4 clamps in the specified clamping range see Fig 2 p 7 Tighten...

Страница 8: ...rvals specified by the inverter manufacturer after switching off the inverter Make sure that the plugs can not be connected unintentionally Before working on the contacts check them for safety extra l...

Страница 9: ...to rotate some modules 180 Module orientation can clearly be identified from the front side by the serial number and barcode labelled behind the module glass on the side with negative connection cabl...

Страница 10: ...by certified personnel The time intervals and extent of the inspection can depend on local circumstances e g salt ammonia content in the air high humidity etc The customer operator must inform himself...

Страница 11: ...tion manual solar modules Q MAXX G2_2020 07_Rev03_AU HANWHA Q CELLS AUSTRALIA PTY LTD Suite 1 Level 1 15 Blue Street North Sydney NSW 2060 Australia TEL 61 0 2 9016 3033 FAX 61 0 2 9016 3032 EMAIL q c...

Отзывы: