3.5.4 Control Module (BMS) and all Battery Modules install into the Rack
Dismantle the
rack metal strip
(on the left side and right side of the rack). After installed the
control module (BMS) and all battery modules need install these two stop blend back.
Install the
buckle nuts
. The position of nuts must meet the position of the control module (BMS)
and all battery modules.
Install the control module (BMS) and all battery modules in. Each module uses 4
screws
to
fix it.
3.5.5 Install the MBMS into a 19’ standard rack [If configured]
Install the
buckle nuts
. The position of nuts must meet the position of the MBMS.
Install the MBMS in. Uses 4
screws
to fix it.
3.5.6 Install the Ethernet Switch into a 19’ standard rack [If configured]
Install the
buckle nuts
. The position of nuts must meet the position of the Ethernet Switch.
Install the Ethernet Switch in. Uses
4 screws
to fix it.